Avenue Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
février 232018

Mining Equipment Mobilization - 24 Hour Work - Avenue Station Main Entrance

WHAT WORK IS TAKING PLACE?

Mining operations will begin at the Avenue Station Main Entrance in Spring 2018. The mining equipment is planned to be delivered to the site during the weekend of March 2 – 4. 

In order to lower the heavy mining equipment to the bottom of the Main Entrance shaft, a temporary crane will be erected on Eglinton Avenue. This crane will take up one additional westbound lane of traffic, just west of Avenue Road. Lire la suite »

février 202018

REPOST & UPDATE: Avenue Station Sewer Lining - East Sewer Section

Original Issue Date: October 14, 2017 (West Sewer Section info)
Updated: January 23, 2018 (East Sewer Section - timing update) 
Updated: February 16, 2018 (East Sewer Section info and timing)
Updated: February 20, 2018 (East Sewer Section - timing update)  Lire la suite »

février 082018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on February 7, 2018. You can see the presentation here:

Download the presentation.

Lire la suite »

janvier 182018

Tunnel Connection Boreholes and Concrete Backfilling for the Main Entrance at Avenue Station

WHAT WORK IS TAKING PLACE?

To prepare for upcoming mining works at Avenue Station, crews need to fill portions of the completed tunnels with concrete. There are two separate phases to this work. Work will begin as soon as January 22, 2018.

PHASE 1 - DRILLING BORE HOLES Lire la suite »

janvier 042018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on January 3, 2018. You can see the presentation here:

Lire la suite »

décembre 212017

Watermain Valve Installation at Avenue Station

WHAT WORK IS TAKING PLACE?

In early January, work will take place to install a valve on the watermain under the south side of Eglinton Avenue. This valve will allow for isolation of the section of the watermain between Avenue Road and Highbourne Road. The closest address to the location of the work is between 253 to 263 Eglinton Ave W.

WHAT TO EXPECT Lire la suite »

décembre 062017

Watermain Lining at Avenue Station Secondary Entrance

Original Issue Date: December 4, 2017
Updated: December 6, 2017
Updated: January 15, 2018 (timing)

 

WATERMAIN LINING AT AVENUE STATION SECONDARY ENTRANCE

Properties 270 – 302 Eglinton Avenue West

WHAT WORK IS TAKING PLACE? Lire la suite »