mai 21 2019

Extended: Upcoming Traffic Changes at Kennedy and Eglinton

Extended: Upcoming Traffic Changes at Kennedy and Eglinton

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, traffic staging at the intersection of Kennedy Road and Eglinton Avenue East will be changing in October. Shoring began in April 2018 and will continue in phases at the intersection. Lire la suite »

mai 10 2019
mai 08 2019

Extended Work Hours Leaside Station

WHAT WORK IS TAKING PLACE?

Beginning as early as May 13, 2019, crews will work extended hours at Leaside Station. Work will be carried out between 5:00 a.m. and 11:00 p.m., Monday through Saturday. Site-based noise mitigation measures have been implemented to reduce disruption due to noise. Lire la suite »

mai 02 2019

Construction Notice: Overnight Hydro Utility Work at Chaplin Station

Overnight Hydro Utility Work at Chaplin Station

Week of May 5 – 10, 2019

Permit Number: 81015401

What Work is Taking Place? Lire la suite »

mai 01 2019

Construction Notice: Lane Reductions to facilitate hydro utility relocation at the East Service Road

Lane Reductions to facilitate hydro utility relocation at the East Service Road

 

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Lire la suite »

avril 25 2019

Construction Notice: Weekend Road Closures for Pile Installation at Chaplin Station May 2019

Weekend Road Closures for Pile Installation at Chaplin Station

May 2019

 (Update: May 2, 2019 - TTC#14 Glencarin Detour Map Added) Lire la suite »

avril 15 2019

Overnight Concrete Pour at Chaplin Station

Overnight Concrete Pour at Chaplin Station
Wednesday April 17, 2019


On Wednesday April 17, 2019, at 2:00 a.m., crews will perform a large concrete pour.  The concrete will form part of the roof of Chaplin Station.  To ensure the continuity and integrity of the activity, and to minimize the impact to TTC operations, the pour will be conducted overnight when traffic is lighter.  Some traffic restrictions will be in effect to accommodate equipment and truck access requirements.  Lire la suite »

avril 11 2019

Equipment Removal at Science Centre Station

EQUIPMENT REMOVAL AT SCIENCE CENTRE STATION

WHAT WORK IS TAKING PLACE? Lire la suite »