Bayview Avenue

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
février 112021

Scaffolding Installation at Leaside Station's Main Entrance -February 15 2021

 

Traffic Configuration

As early as February 15, 2021, crews at Leaside Station will begin to install a temporary scaffolding system along the east wall of the Main Entrance site to provide overhead protection and delineation for the work zone.  Scaffolding installation will take place within the work zone between 7:00 a.m. – 11:00 p.m. for approximately two (2) days. The scaffolding system will remain in place for approximately four (4) months.

  Lire la suite »

février 102021

Update: Extended Construction Hours at Leaside Station - February 2021

 

Traffic Configuratoin

Through Summer 2021, crews at Leaside Station will continue to work extended construction hours at the station entrances and in the station box below Eglinton Avenue. Construction activities include waterproofing, placement of rebar and steel, formwork installations, mechanical electrical works, and concrete pours.

  Lire la suite »

janvier 192021
novembre 242020

Cancellation: Fire Hydrant Removal at Eglinton Avenue East and Donlea Drive - November 19 – November 20, 2020

 

 

What Work is Taking Place?

*This work has been CANCELLED UNTIL FURTHER NOTICE as of November 24th, 2020*

From November 19 – November 20, 2020, crews will work to remove an abandoned fire hydrant at the north-east corner of Eglinton Avenue East and Donlea Drive. This work is expected to take place from 6:00 a.m. – 5:00 p.m. Lire la suite »

novembre 112020

Notice of Utility Works at Bayview and Glazebrook Avenues - November 13 2020

Notice of Utility Works at Bayview and Glazebrook Avenues

What Work is Taking Place?


On Friday November 13, 2020, crews at Leaside Station will perform utility works within the left turn lane on Bayview Avenue at Glazebrook Avenue. Work will take place between 10:00 a.m. – 1:00 p.m.

octobre 222020

Fall Virtual Open House: Central

Thank you for your interested in the Central Virtual Open House (Chaplin to Leaside Stations) on October 21, 2020. The presentation is here:

 

Lire la suite »

octobre 012020

Extended Construction Hours at Leaside Station - Late September 2020

What Work Is Taking Place?

In Summer 2020, crews completed excavation works at Leaside Station. Permanent works are currently taking place within the Station Box beneath Eglinton Avenue and at the Main, and Secondary Entrance sites. Permanent works are construction activities that shape the final station structure underground. These activities include waterproofing, placement of rebar/steel, mechanical and electrical installations, and concrete pours. Lire la suite »

septembre 092020

Update: Overnight Decking Reinstatement Work at Leaside Station

Monday September 14 –  Friday September 18, 2020

What Work is Taking Place? Lire la suite »

juillet 312020

UpdateOvernight Decking Reinstatement Work at Leaside Station July 27, 2020 – August 8, 2020.

What Work is Taking Place?
From Tuesday August 4 – Saturday August 8, 2020 crews at Leaside Station will work overnight to reinstate the road decking at Eglinton Avenue East and Bayview Avenue. Work will be performed throughout all areas of the intersection, with crews occupying one lane on Eglinton Avenue East and Bayview Avenue, during each night of work.

Lire la suite »

Catégories: