Bayview Avenue

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
janvier 082016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »

janvier 082016

Sewer Work – Eglinton Avenue East between Banff Road and Bayview Avenue

What: To prepare for west headwall construction for the future Bayview Station, crews are rehabilitating and upgrading an existing underground sewer on Eglinton Avenue East between east of Banff Road and west of Bayview Avenue. 

When: Work began in December, 2015, and will continue for several weeks. Work may be rescheduled or adjusted due to weather conditions or unforeseen circumstances.

Please be advised:  Lire la suite »

décembre 072015

OVERNIGHT CONSTRUCTION AT BAYVIEW/EGLINTON INTERSECTION

What work is starting?

What: Installation of a jet-grout delivery trench within the intersection of Bayview Avenue and Eglinton Avenue.

When:   Lire la suite »

novembre 242015

Temporary Sewer Work - Walder Avenue

What work is starting?

What: In conjunction with the nearby Eglinton Avenue East sewer rehabilitation work, crews will be excavating for temporary bypass pipes on the west side of Walder Avenue in the southbound lane.  

Why:  A major sewer under Eglinton Avenue East requires upgrading prior to tunnel excavation. Lire la suite »

novembre 052015

Tunnelling for the Crosstown: What you may experience

As you know, tunnelling continues on the Eglinton Crosstown Light Rail Transit (LRT) project as we build the underground portion of the future transit line. 

The tunnel boring machines (TBMs) operate around the clock - 24 hours a day, seven days week. On average, they each travel about 10 metres per day. Our TBMs are working about 20 metres below ground, but we do sometimes hear from nearby residents who may experience vibration from the TBMs as they pass through the area.    Lire la suite »

octobre 142015

Stage 1: Bayview Headwall Construction

What work is starting?

What: Crews will be constructing the east headwall for the future Bayview station in advance of the twin tunnel construction. Headwalls are underground support walls located at the east and west ends of the future station location. This work will include heavy civil construction; installation of secant piles which includes the use of a large drill-rig, jet grouting, daylighting and relocating utilities. Lire la suite »

octobre 052015

Eglinton Crosstown Construction Update

Metrolinx is making progress on the Crosstown project. Construction of a launch shaft east of Brentcliffe Road is complete and assembly of two tunnel boring machines (TBMs) is nearing completion. Utility relocation and headwall construction along Eglinton Avenue East between Brentcliffe and Bayview started in January 2014. Some works along the road have been completed and others are progressing well. The Crosstown Team appreciates the patience of our neighbours while we work to build transit. Lire la suite »

octobre 012015

Eglinton Crosstown Line Station and Stop Names

The Eglinton Crosstown Project is building the Eglinton Line, a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilometre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today.    Lire la suite »

septembre 252015

East tunnel boring machines begin their journey!

The Eglinton Crosstown LRT tunnel boring machines 'Don' and 'Humber' will begin their journey westward on September 29, 2015, marking another milestone toward the completion of the new LRT. 

The westbound tunnelling will start from the launch shaft located east of Brentcliffe Rd. and will proceed towards Yonge St. Work on the western segment of the tunnel has been underway since June 2013 with four of the 6.5 kilometres already complete. All tunnelling work is expected to be finished by the end of 2016. Lire la suite »