décembre 202017

Updated: Truck Staging on Roehampton Avenue for Leaside Station

What Work is Taking Place?

To facilitate shoring operations currently underway at Leaside Station, construction vehicles will periodically occupy the eastbound lane of Roehampton Avenue, west of Bayview Avenue. The lane will be used to accommodate temporary and periodic staging of trucks while other trucks are loading and offloading materials within existing construction zones. Truck staging will not block any driveways or entrances to businesses. Lire la suite »

décembre 152017

Stage 2: Support of Excavation Works at Leaside Station

 

Original Issue Date: December 15, 2017

Updated: December 28, 2017

What Work is Taking Place? Lire la suite »

décembre 152017

Overnight Traffic Set Up at Leaside Station for Stage 2

Original Issue Date: December 15, 2017

Updated: December 28, 2017 Lire la suite »

décembre 072017

Bell Utility Relocations and Watermain Investigations for Leaside Station

What Work is Taking Place?

Beginning as early as December 11th, Bell utility relocations and watermain investigations will take place in the vicinity of Eglinton Avenue East and Bayview Avenue. Works are short duration and will begin within the existing work zone at the main entrance. Work taking place outside the existing work zone will occur on Eglinton Avenue, east of the main entrance. Lire la suite »

novembre 092017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on November 8, 2017. You can see the presentation here:

Lire la suite »

novembre 072017

Traffic Changes at Leaside Station

What Work is Taking Place?

Starting as soon as Thursday, November 9th, there will be a couple of changes to the existing traffic set up around Eglinton Avenue and Bayview Avenue:

Left turn restriction from Mann Avenue to westbound Eglinton Avenue East Lire la suite »

novembre 032017

Utilities Works at Leaside Station

What Work is Taking Place?

On Monday November 6th, work will be completed to bring power to the secondary entrance area. A small work zone will be in place on the west side of Bayview Avenue near the driveway access to the Metro Parking.

Minor utility works occur periodically within the current construction zones with no additional traffic or pedestrian impacts. Lire la suite »

octobre 172017

Wet Utilities Relocations at Leaside Station

What Work is Taking Place?

To support the ongoing construction works at the future Leaside Station, wet utilities infrastructure under Eglinton Avenue East will be relocated. The first stage of the work will take place in the existing work zone on the south side of Eglinton Avenue East just east of Mann Avenue. Work to relocate utilities on the north side of Eglinton Avenue East will take place in 2018. Lire la suite »

octobre 122017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on October 11, 2017. You can see the presentation here: Lire la suite »