Birchmount Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
octobre 292020

Overnight OCS Cable Works on Eglinton Ave between Birchmount Road and Ionview Road - November 4-5, 2020

 

 

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Birchmount Road and Ionview Road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles).  Installation will take place overnight November 4-5, 2020 between the hours of 9:00 p.m. and 6:00 a.m.

  Lire la suite »

octobre 222020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late December 2020

 

 

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late December 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work.

 

What to Expect Lire la suite »

octobre 082020

(Updated) Glazing Installation at Golden Mile, Birchmount, O'Connor and Wynford Stops

UPDATED OCTOBER 23, 2020

What Work is Taking Place?

Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters.  Glazing consists of glass Installation works for the LRT shelters.

What to Expect Lire la suite »

septembre 302020

Overnight Track Works on Eglinton Ave East between Birchmount and Kennedy Road - October 5-9, 2020

 

 

What Work is Taking Place?

Crews will be installing and performing welding activities on the LRT tracks within the guideway work zone on Eglinton Avenue East between Birchmount Road and Kennedy Road. Work will take place October 5-9, 2020 between the hours of 5:00 p.m. and 3:30 a.m.

 

What to Expect Lire la suite »

septembre 302020

Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on September 29, 2020. You can see the presentation here:

 


Lire la suite »

septembre 232020

Late Night Concrete Pour at Birchmount Road and Eglinton Avenue East - September 24, 2020

 

 

What Work is Taking Place?

On September 24, 2020, crews will perform a late-night concrete pour on Eglinton Avenue East, West of Birchmount Road. The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.  The pour will take place between the hours of 10:00 p.m. and 3:00 a.m.  Lire la suite »

septembre 142020

Birchmount Stop Permanent Left Turn Removal - September 15, 2020

 

What Work isTaking Place?

To accommodate the continued construction of Birchmount Stop and as part of the final intersection configuration, the eastbound left turn movement at Eglinton Avenue East and Birchmount Road will be permanently removed as early as September 15, 2020. 

The westbound left turn movement was removed permanently late 2019.

 

What to Expect Lire la suite »