Don Mills Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
avril 202018

Large Tower Crane Delivery at Science Centre Station

What Work is Taking Place?

On Saturday, April 28, 2018, a large tower crane will be delivered to Science Centre Station. The tower crane will be erected within the existing construction zone on Eglinton Avenue East, west of Don Mills Road.    Lire la suite »

avril 122018

REISSUE: LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station

What Work is Taking Place?

Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station. Lire la suite »

avril 062018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on April 5, 2018. You can see the presentation here:

Lire la suite »

mars 292018

Central-East Open House (Laird Station to West At-Grade (Sunnybrook - O'Connor Stops)

Thank you for attending the open house about Laird Station to West At-Grade (Sunnybrook - O'Connor Stops) on March 28, 2018.

For those of you who missed it, the presentation is here: Lire la suite »

mars 282018

Clearing, Grubbing, and Pruning between Don Avon Drive to Victoria Park Avenue in Preparation for Construction of Surface Stops

As our constructors get ready to ramp up construction activity at the surface section of the Eglinton Crosstown LRT project, clearing, grubbing, and pruning and protection activity continues as part of preparatory work. This activity commenced two years ago and is done on an ongoing, as-needed basis to support the construction of the Eglinton Crosstown Light Rail Transit Project (ECLRT). All works will be carried out with the approvals and cooperation of the responsible authority. Lire la suite »

mars 092018

Overnight Road Repair Work Starting March 12 - Traffic Lane Reductions at Don Mills & Eglinton

What Work is Taking Place?

Ongoing road maintenance continues around the Don Mills Road and Eglinton Avenue East intersection. The rebuilding of catch basins on Eglinton Avenue East between the DVP and Don Mills Road will start on Monday, March 12, 2018 for approximately one week.

To minimize traffic disruption for the community, transit users and local businesses, this work is being done overnight.

Hours of Work Lire la suite »

mars 062018

LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station

What Work is Taking Place?

Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station.

Starting in mid-March for approximately three (3) weeks, work to connect the new watermain section to the existing infrastructure will take place. During these works, residents in the catchment area may experience lower than normal water pressure. Lire la suite »

mars 022018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:

Lire la suite »

février 272018

Overnight Piling Work February 28 for Science Centre Station

What Work is Taking Place?

Crews will be drilling piles within the Don Mills Road and Eglinton Avenue East intersection as part of the Support of Excavation work at the future Science Centre Station. 

Due to the location of the piles and in an effort to minimize disruption to local traffic and commuters work will be performed overnight on Wednesday, February 28, 2018 from 8:00 p.m. to 5:00 a.m. Thursday morning. The intersection will be restored in advance of morning rush hour. Lire la suite »