Overnight Concrete Pour at Fairbank Station - May 30, 2019

What Work is Taking Place?

On Thursday May 30th, crews will perform a 650m3 concrete pour at Fairbank Station. The concrete will form the base of the second level concourse at the main entrance. Concrete pumps will be placed in the work zone, and concrete trucks will queue in the southbound lane of Dufferin Street between Eglinton Avenue West and Hunter Street as well as the west curb lane of Vaughan Road. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.  Lire la suite »

mai 132019

Overnight Concrete Pour at Fairbank Station - May 16, 2019

What Work is Taking Place?

On Thursday May 16, 2019, crews will perform a large concrete pour at the northwest station box of Fairbank Station. The concrete will form the part of the roof of the station.  Concrete pumps will be placed in the work zone, and concrete trucks will queue in the westbound curb lane of Eglinton Avenue, east of Dufferin Street, and on Livingstone Ave between Dufferin St and the parking lot.  Dufferin Street and Eglinton Avenue West will remain open while work takes place.  Lire la suite »

mai 022019

Upcoming Traffic Configuration Change at Fairbank Station

What Work is Taking Place?

As early as May 6, 2019, the traffic configuration at Dufferin Street and Eglinton Avenue will change to accommodate the next stage of construction.  Traffic on Eglinton Avenue will be shifted south and construction will return to the north side of Eglinton Avenue between Shortt Street and Dufferin Street.  The work zone on the north side of Eglinton Avenue, east of Dufferin Street will remain in place.

Hours of Work  Lire la suite »

avril 162019

Construction Notice: Concrete Pour at Fairbank Station - April 18, 2019

What Work is Taking Place?

On Thursday April 18, crews will perform a concrete pour at the Main Entrance area of Fairbank Station. The concrete will form part of the Main Entrance walls.  A concrete pump will be placed on Vaughan Road behind the Main Entrance site, and concrete trucks will deliver concrete to the site.  Dufferin Street and Eglinton Avenue West will remain open while work takes place. Lire la suite »

avril 112019

Pedestrian Route Change at Fairbank Station April 11, 2019

What Work is Taking Place?

On Thursday April 11, 2019, a portion of the pedestrian rerouting (shown in red below) around the southwest work zone will be removed to make way for road reinstatement works.  The area will remain closed until the next traffic configuration change.

Details

  • Beginning April 11, 2019 through to the end of April 2019

  Lire la suite »

avril 102019

Concrete Pour at Fairbank Station April 12, 2019

What Work is Taking Place?

On Friday April 12, crews will perform a concrete pour at the Main Entrance area of Fairbank Station. The concrete will form part of the Main Entrance walls.  A concrete pump will be placed on Vaughan Road behind the Main Entrance site, and concrete trucks will deliver concrete to the site.  Dufferin Street and Eglinton Avenue West will remain open while work takes place.

Hours of Work  Lire la suite »

avril 022019

Daytime Concrete Pour at Fairbank Station - April 3, 2019

What Work is Taking Place?

On Wednesday April 3, crews will perform a concrete pour at the Main Entrance area of Fairbank Station. The concrete will form part of the Main Entrance walls.  A concrete pump will be placed on Vaughan Road behind the Main Entrance site, and concrete trucks will deliver concrete to the site.  Dufferin Street and Eglinton Avenue West will remain open while work takes place.

Hours of Work Lire la suite »

avril 022019

Temporary Crosswalk Removal at Fairbank Station April 3 – 9, 2019

What Work is Taking Place?

The east crosswalk at Dufferin Street and Eglinton Avenue West will be temporarily unavailable for approximately one week while crews perform drilling work on the southeast corner.  During this time, the west crosswalk will remain open.  Upon completion of the work, the east crosswalk will be restored.

 