août 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Lire la suite »

août 242017

Fairbank Station Public Information Session

Thank you for attending the public information session about design plans of the parkette for the new Fairbank Station on August 23, 2017. 

For those of you who missed it, the presentation is here: Lire la suite »

août 092017

Fairbank-Oakwood Construction Liaison Committee Meeting

The construction liaison committee meeting of Fairbank and Oakwood stations was held on August 8, 2017. You can see the presentation here:

Lire la suite »

juillet 212017

Watermain Service Work at Fairbank Station

What work is taking place?

Beginning as early as July 24, crews will be performing water main service work in the vicinity of Dufferin Street and Eglinton Avenue West. The work will take place primarily in the existing work zones, but temporary pedestrian rerouting around work zones may be in effect. Lire la suite »

mai 172017

Watermain Valve Installation and Servicing Work at Fairbank Station

Watermain Valve Installation and Servicing Work at Fairbank Station 

 

What work is taking place? Lire la suite »

mai 162017

Shoring and Utilities Relocation in the Roadway at Fairbank Station

 

What work is taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In mid-May 2017, crews will begin shoring of the station box, as well as wet utilities relocation, starting on the north side of Eglinton Avenue East.  Lire la suite »

avril 072017

Fairbank and Oakwood Stations Open House

Thank you for attending our Fairbank and Oakwood Stations Open House on April 6, 2017.

For those of you who missed it, the presentation is here:

Lire la suite »

avril 032017

Traffic Signal Hanging at Fairbank Station

What Work is Taking Place?

To make way for station construction, crews must relocate and hang the existing traffic signals at Dufferin Street and Eglinton Avenue West.  Traffic signal relocation will take place over five days, with curbside lane closures throughout the intersection.  Crews will install temporary traffic poles and signals at each corner of the intersection.  The temporary traffic signals and cables will be hung overhead, while the existing traffic poles are removed. Lire la suite »

mars 312017

LOW WATER PRESSURE NOTICE: Watermain Investigation Work

What Work is Taking Place?

On April 3, 2017, crews will begin subsurface utility engineering (SUE) investigation of a large 900mm watermain in the Eglinton Avenue West and Chaplin Crescent area.  The watermain will be exposed to determine the utility and ground conditions in advance of wet utilities relocation.  Most of the work will take place within the existing traffic staging at Chaplin Crescent and Eglinton Avenue West. Lire la suite »