novembre 12 2020

Sidewalk Construction at Eglinton Ave E and Hakimi and Lebovic Ave

 

WHAT WORK IS TAKING PLACE?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi and Lebovic Ave intersection. Work on the west side of the intersection is expected to begin November 12, 2020 for a period of one week. Work on the east side of the intersection is expected to begin November 23, 2020 for a period of one week.

 

novembre 11 2020

Notice of Utility Works at Bayview and Glazebrook Avenues - November 13 2020

Notice of Utility Works at Bayview and Glazebrook Avenues

What Work is Taking Place?


On Friday November 13, 2020, crews at Leaside Station will perform utility works within the left turn lane on Bayview Avenue at Glazebrook Avenue. Work will take place between 10:00 a.m. – 1:00 p.m.

novembre 11 2020

Sidewalk Construction on Eglinton Ave, East of Sloane Avenue

 

What Work is Taking Place?

Crews will be constructing final sidewalks on the north side of Eglinton Avenue East, east of Sloane Avenue. Driveway tie-in works will also be performed at the Eglinton Ave East entrance for the condominiums at 1700, 1720 and 1730 Eglinton Avenue East. Work is expected to begin as early as November 11, 2020 and continue for approximately two weeks.

novembre 05 2020

Sidewalk Construction at Eglinton Ave E and Pharmacy Ave intersection - East Side

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the north-east and south-east corners of the Eglinton Ave E and Pharmacy Ave intersection. Work is expected to begin November 6, 2020 for a period of approximately one week.

 

What to Expect

Catégories:
octobre 26 2020

Berwick Road Closure for Concrete Pour

What Work Is Taking Place?

On Monday October 26, 2020, Berwick Avenue will be closed at Yonge Street while a concrete pour will be carried out at the Berwick Portal site.  The concrete will form part of the portal foundation.  A concrete pump will be placed on Berwick Avenue and several concrete trucks will enter the site each hour.

What to Expect

octobre 19 2020

Curb and Sidewalk Restoration on Gervais Drive at Eglinton Ave East - October 26 2020

Curb and Sidewalk Restoration on Gervais Drive at Eglinton Ave East

What Work is Taking Place?

Crews will be performing sidewalk, curb and road restoration works on the west side of Gervais Drive, north of Eglinton Avenue East. To accommodate these activities, a traffic change will be implemented and remain in place for approximately three (3) weeks.

What to Expect Lire la suite »

Catégories:
octobre 02 2020

POSTPONED: Eglinton Avenue West Road Closure for Tower Crane Relocation at Oakwood Station - October 9-10, 2020

Edited October 6: *This work has been postponed to a future date, yet to be determined.*

What Work is Taking Place? Lire la suite »

octobre 01 2020

Traffic Configuration Change at Forest Hill Station

Original Post: September 28, 2020

Updated: October 1, 2020

 

What Work Is Taking Place? Lire la suite »