Ionview Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
novembre 072018

Left Lane Restrictions at Ionview Road and Eglinton Avenue East

What Work is Taking Place?

Due to an unforeseen issue, there will be left-turn restrictions at Ionview Road and Eglinton Avenue East beginning as early as Wednesday, November 7, 2018. Crews are currently working on a long-term resolution. 

We apologize for the inconvenience this may cause.

Lire la suite »

octobre 312018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:

Lire la suite »

septembre 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:

Lire la suite »

août 162018

UPDATE: Watermain, Storm and Sanitary Relocation from Ionview Road to Kennedy Road for Future Kennedy Station

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between Ionview Road and Kennedy Road.

Crews continue to work on installing the new storm and sanitary system from Ionview to Kennedy and will complete their work with a final connection to the existing manholes located within the Kennedy and Eglinton intersection. Lire la suite »

juin 272018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committe meeting of Pharmacy to Kennedy was held on June 26, 2018. You can see the presentation here:

mai 302018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on May 29, 2018. You can see the presentation here:

Download the presentation

mai 252018

UPDATE: Watermain, Storm and Sanitary Relocation between Ionview Road and Rosemount Drive

Originally Published: May 25, 2018

Updated: May 28, 2018

Updated: May 29, 2018

What Work is Taking Place?

As part of construction of the future Kennedy Station, crews continue to upgrade and relocate wet utilities along Eglinton Ave between east of Birchmount Road to west of Midland Avenue, including the North Service Road. Lire la suite »

mai 172018

EXTENDED: Temporary Closure of Ionview Road

What Work is Taking Place?

Storm and sanitary utilities relocation work continues at Ionview Road and Eglinton Avenue East following temporary closure of Ionview Road at Eglinton Avenue East on Monday, May 7th, 2018. This also involves executing an east-west crossing at Ionview Road. The work is part of a larger upgrade and relocation of utilities as part of the Eglinton Crosstown LRT. Lire la suite »

avril 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on April 24, 2018. You can see the presentation here: 

avril 122018

East Open House: East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station

Thank you for attending the open house about East At-Grade (Pharmacy - Ionview Stops) to Kennedy Station on April 11, 2018.

For those of you who missed it, the presentation is here: Lire la suite »