Ionview Road
À la recherche de nouvelles concernant des travaux près d’une i
Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.
- Black Creek Drive
- Keele Street
- Caledonia Road
- Dufferin Street
- Oakwood Avenue
- Allen Road
- Bathurst Avenue
- Chaplin Crescent
- Avenue Road
- Yonge Street
- Mount Pleasant Road
- Bayview Avenue
- Donlea Drive/Hanna Road
- Laird Drive
- Leslie Street
- Don Mills Road
- Ferrand Drive
- Wynford Drive
- Bermondsey Road
- Victoria Park Avenue
- Pharmacy Avenue
- Lebovic Avenue
- Warden Avenue
- Birchmount Road
- Ionview Road
- Kennedy Road
- Little Blvd.
- Petman Avenue
- Brentcliffe Road
- Allen Road
- Avenue Road
- Bathurst Avenue
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Lebovic Avenue
- Leslie Street
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Wynford Drive
- Warden Avenue
- Yonge Street

UPDATED: Permanent Sidewalk and Curb Installation between Birchmount Road to Kennedy Road - April 27, 2020
Original Post: April 14, 2020
Latest update: April 20, 2020
What Work is Taking Place
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent curbs and sidewalks on the north and south side of Eglinton Avenue East, between Birchmount Road and Kennedy Road. Lire la suite »
Virtual Open House: Eastern Works
The virtual open house for stations and stops between Don Mills Road and Kennedy Road was held on April 9, 2020. You can view the presentation here:
Driveway Closures and Boulevard Restoration Works: Rosemount Drive to Kennedy Road - April 20, 2020
What Work is Taking Place
As part of the ongoing construction for the future surface alignment of the Eglinton Crosstown LRT, crews will begin driveway tie-ins and boulevard restoration on Eglinton Avenue East, between Rosemount Drive and Kennedy Road. Partial or full driveway closures may be required at some properties along Eglinton Avenue East to ensure that driveways are aligned with the grading of the road. Lire la suite »
Stop Construction at Ionview Road
What Work is Taking Place
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be working on stop construction at Ionview Road, beginning Monday April 6, 2020 and lasting for two (2) weeks.
Guideway and stop construction includes, cutting and removal of asphalt, excavation, installation of subgrade materials, duct banks installation, track drainage, track slab and stop construction.
Work Area Map Lire la suite »
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2020
Construction Liaison Committee of Pharmacy to Kennedy was held on March 31, 2020. You can see the presentation here:
Sidewalk and Partial Driveway Closure at 2239 and 2243 Eglinton Avenue East - Extended until July 31
Last update: January 9, 2020
Updated on March 27, 2020
What Work is Taking Place
As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews continue work with stage two at Massey Creek. There will be a partial driveway closure to the driveway access for 2239 and 2243 Eglinton Avenue East. The partial driveway restriction will be extended through July 31 in order to carry out the remaining work safely. Access to the properties will be maintained at all times. Lire la suite »
Closure on Rosemount Drive North of Eglinton Avenue East - Extended Until April 1, 2020
What Work is Taking Place
As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended until April 1, 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work.
Work continues at the east wing-wall of the creek and includes excavation, concrete works, removal of form work and backfilling. Lire la suite »
Extended Construction Hours at Massey Creek Culvert - February 4, 2020
WHAT WORK IS TAKING PLACE
As part of the ongoing construction of the Eglinton Crosstown LRT, crews continue rehabilitation and reconstruction of the Massey Creek culvert at the Eglinton Avenue East and Rosemount Drive intersection.
Starting February 4, 2020, for a maximum period of three (3) weeks, crews will work extended hours to accelerate construction. Construction activities will include excavation, welding, rebar, formwork and concrete works. Lire la suite »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on January 28, 2020. You can see the presentation here:
UPDATED: Mid-block Guideway and Stop Construction from Victoria Park Avenue to Ionview Road
Original Post: November 15, 2019
Updated: January 6, 2020
What Work is Taking Place
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting mid-block guideway and stop construction between Victoria Park Avenue and Ionview Road, for approximately eight (8) months through spring 2020. Lire la suite »