Kennedy Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
septembre 252019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:

 

Download the presentation

septembre 092019

Extended: Upcoming Traffic Changes at Kennedy and Eglinton

Original Post: May 21, 2019

Updated: September 9, 2019

 

Extended: Upcoming Traffic Changes at Kennedy and Eglinton

What Work is Taking Place? Lire la suite »

mai 282019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on May 28, 2019. You can see the presentation here:

Lire la suite »

mai 012019

Construction Notice: Lane Reductions to facilitate hydro utility relocation at the East Service Road

Lane Reductions to facilitate hydro utility relocation at the East Service Road

 

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Lire la suite »

avril 302019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:

Lire la suite »

avril 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:

Download the presentation

mars 272019

Upcoming Bus Route Flips at Kennedy Station to accommodate shoring at the SRT

What Work is Taking Place?

As part of the continued support of excavation works (shoring) and utility relocations for the future Kennedy Station, crews will be conducting a series of bus flips in the vicinity of the Scarborough Rapid Transit (SRT) - Line 3 at Kennedy Road. Lire la suite »

mars 262019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on March 26, 2019. You can see the presentation here:

Lire la suite »

mars 052019

Overnight Sanitary Pipe Installation between Ionview Road and Kennedy Road

What Work is Taking Place?

In support of the construction of the future Kennedy Station, crews will be conducting sanitary pipe installation activities in the center of Eglinton Avenue East, between Ionview Road and Kennedy Road. This work is expected to begin as early as March 6, 2019 and lasting for approximately one (1) week.

In an effort to minimise disruption and to protect the safety of the local community and commuters, work will be performed overnight.

Stage 1    Lire la suite »

février 252019

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, February 28, 2019 from 4:00 a.m. until 4:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west Eglinton Avenue East.

Stage 1 Lire la suite »