Kennedy Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
mai 132021

Light Rail Vehicle Delivery and Testing between Laird Dr. and Kennedy Rd.

 

East Testing and Commissioning Map

Starting May 25, six (6) Light Rail Vehicles (LRVs) will be moved from the Eglinton Maintenance and Storage Facility (EMSF) to the LRT tracks (guideway) at Rosemount Dr. via truck transport. The LRVs will be delivered one at a time, on May 25, 26, 27, 31 and June 1 and 2. 

  Lire la suite »

avril 302021

Overhead Catenary System Energization between Laird Drive and Kennedy Road

On May 3, 2021, the overhead catenary system (OCS) between Laird Drive and Kennedy Road will be energized. Once energized the OCS cables are electrified and dangerous if encountered. It is never safe to go near the OCS. Please obey signage and stay away from all overhead cables.

The OCS installed above the LRT tracks and powers the Light Rail Vehicles (LRVs). Power is delivered from traction power substations located along the alignment to the LRVs via the OCS cables. Lire la suite »

avril 072021

Tower Crane Removal at Kennedy Station April 7, 2021

 

What Work is Taking Place?

As part of the construction of the future Kennedy Station, crews will be removing a tower crane within the construction zone at Kennedy Station, south of Eglinton Avenue East.

 

What to Expect

avril 022021

Utility Crossing Work and Track Resurfacing at Kennedy Station's GO Corridor April 2-4, 2021

What Work is Taking Place?

Crews at Kennedy Station continue with GO corridor development, including utility installations. From Friday April 2 until Sunday April 4, crews will be installing utility casing crossings within the GO track area, followed by track resurfacing. Crews will be working from as early as 6:00am until 11:00pm.

 

What to Expect

février 262021

Overnight OCS Cable Installation on Eglinton Ave at Laird, Leslie, Sloane & Kennedy. March 1 - April 2

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton avenue east between Laird drive, Leslie street, Swift drive, Sloane avenue, and Kennedy road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles). Lire la suite »

février 112021

UPDATED: Traffic Change at Kennedy Station, East of Kennedy Road - February 11,2021

UPDATE: Photo updated to show current traffic configuration. Work is ongoing until summer 2021.

février 082021

Overnight Utility Inspection at Rosemount Dr and Eglinton Ave E

 

What Work is Taking Place?

Crews at Rosemount Drive and Eglinton Avenue East continue with utility activities. Overnight on Monday February 8, crews will be inspecting the existing utilities in the area, from as early as 11:30pm until 5:00am on Tuesday February 9. All current traffic restrictions at the intersection will remain in place.