Laird Drive

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
septembre 102020

Laird Station Extended Hours - September 14, 2020

September 14, 2020

What Work is Taking Place?

Beginning September 14, 2020, crews will begin working extended hours at Laird Station to accommodate concrete and formwork activities in the tunnel and entrance shafts.

What to Expect Lire la suite »

septembre 092020

Laird Station Concrete Pour - September 10, 2020

September 10, 2020

What Work is Taking Place?

Beginning September 10, 2020, crews will perform a concrete pour at the main entrance at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m.

What to Expect Lire la suite »

septembre 092020

Laird Station Concrete Chipping Works - September 10, 2020

Monday September 14 –  Friday September 18, 2020

What Work is Taking Place? Lire la suite »

août 062020

Sidewalk and Lane Closure at Laird Station Friday August 7, 2020

What Work Is Taking Place?
On Friday August 7, 2020, crews will perform a concrete pour at the Laird Station Main Entrance site.  The work will be performed using a mobile crane and several concrete trucks.  The eastbound curb lane on Eglinton Avenue East, the south sidewalk in front of Laird Station Main Entrance as well as the west and south crosswalks at Laird Drive and Eglinton Avenue East will be closed while this work takes place.  Upon completion of the pour, the lane, sidewalk and crosswalks will re-open. Lire la suite »

Catégories:
juillet 272020

Laird Station 24-Hour Concrete Pour

What Work is Taking Place?
Beginning July 29, 2020, crews will perform a 24-hour concrete pour at the main entrance at Laird Station. Work will begin preparatory work as early as 5:00 a.m. and the pour will be ongoing for approximately 24 hours.  

  Lire la suite »

Catégories:
juin 252020

Decommissioning Monitoring Wells - Zone 8 - Laird to Brentcliffe

 

Decommissioning Monitoring Wells between Laird Drive and east of Brentcliffe Road Lire la suite »

juin 162020

Laird Station Construction Updates

LAIRD STATION CONSTRUCTION UPDATE

JUNE 2020 Lire la suite »

juin 152020
juin 012020

Concrete Pour at Laird Station

CONCRETE POUR AT LAIRD STATION

June 1, 2020 Lire la suite »

mai 282020

Decommissioning Monitoring Wells between Taunton Road and Laird Drive

Decommissioning Monitoring Wells between Taunton Road and Laird Drive Lire la suite »