Laird Drive

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
novembre 172020

Laird Station Overnight Backfilling Works - November 18 2020

What Work is Taking Place?

As early as November 18, 2020, crews will begin backfilling activities at the south west corner of Eglinton and Laird Drive. Work will take place between the hours of 9:00p.m. to 5:00 a.m. Monday to Saturday for a period of two (2) weeks.

 

What to Expect

novembre 132020

Concrete Pour at Laird Station - November 14, 2020

 

 

What Work is Taking Place?

Beginning November 14, 2020, crews will perform a concrete pour at the main entrance work zone at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m. 

 

What to Expect Lire la suite »

novembre 132020

UPDATE: Extended Hours at Laird Station

What Work is Taking Place?

Overnight working hours began at the main entrance on September 30, 2020. It has now been extended through to December 18, 2020. Permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday. The current extended hours (6:00 a.m. – 1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year. Lire la suite »

octobre 012020

Updated: Extended Hours at Laird Station (24 hour work) - September 30, 2020

What Work is Taking Place?

As early as September 30, 2020, permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday for approximately five (5) weeks. The current extended hours (6:00 a.m. -1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year.

septembre 102020

Laird Station Extended Hours - September 14, 2020

September 14, 2020

What Work is Taking Place?

Beginning September 14, 2020, crews will begin working extended hours at Laird Station to accommodate concrete and formwork activities in the tunnel and entrance shafts.

What to Expect Lire la suite »

septembre 092020

Laird Station Concrete Chipping Works - September 10, 2020

Monday September 14 –  Friday September 18, 2020

What Work is Taking Place? Lire la suite »

septembre 092020

Laird Station Concrete Pour - September 10, 2020

September 10, 2020

What Work is Taking Place?

Beginning September 10, 2020, crews will perform a concrete pour at the main entrance at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m.

What to Expect Lire la suite »

août 062020

Sidewalk and Lane Closure at Laird Station Friday August 7, 2020

What Work Is Taking Place?
On Friday August 7, 2020, crews will perform a concrete pour at the Laird Station Main Entrance site.  The work will be performed using a mobile crane and several concrete trucks.  The eastbound curb lane on Eglinton Avenue East, the south sidewalk in front of Laird Station Main Entrance as well as the west and south crosswalks at Laird Drive and Eglinton Avenue East will be closed while this work takes place.  Upon completion of the pour, the lane, sidewalk and crosswalks will re-open. Lire la suite »

Catégories: