Update: Extension of Intermittent Sidewalk Closures at Mount Pleasant Station Friday, October 18, 2019

Starting Friday October 18, the sidewalk on the north side of Eglinton Ave E will be closed intermittently for one (1) week to accommodate ongoing piling work at Mount Pleasant Station. Intermittent sidewalk closures will take place from the north-easterly corner of Mt Pleasant Rd. and Eglinton Ave to 300 Eglinton Ave. The closures will take place between 7 a.m. – 9 p.m. Access to the surrounding buildings and TTC will be maintained at all times. Lire la suite »

octobre 162019

Central Open House

Thank you for attending the Central Open House on October 15, 2019. For those of you who missed it, the presentation is here:

Download the presentation

octobre 042019

Intermittent Sidewalk Closure at Mount Pleasant Station Monday, October 7, 2019

On Monday October 7, there will be an intermittent sidewalk closure on the north side of Eglinton Ave E to complete piling work at Mount Pleasant Station. The sidewalk on the north side of Eglinton Ave E will be closed from the north-easterly corner of Mt Pleasant Rd. and Eglinton Ave to 300 Eglinton Ave E. The sidewalk closure will begin as early as  7 a.m. and take place for approximately five (5) hours. Access to the surrounding buildings and TTC will be maintained at all times. Traffic control personnel will be present while this closure takes place. Lire la suite »

octobre 042019

Extended Construction Hours at Mount Pleasant Station Beginning October 2019

 

Starting Tuesday October 15, crews will begin working extended hours at Mount Pleasant Station to accelerate construction.  Extended hours work will be completed in phases, beginning with shallow excavation and roof construction from October 2019 through February 2020.  On-site mitigation measures will be in place to minimize disruption caused by this work.  Lire la suite »

septembre 302019

Updated: Traffic Change at Mount Pleasant Station Thursday, October 4, 2019

As early as Thursday October 3, a new traffic configuration will be implemented at Mount Pleasant Station. East of the intersection, the island in the middle of Eglinton Avenue at Taunton Rd will be removed and traffic will shift fully to the south side of Eglinton Avenue. On Mt Pleasant Rd, traffic will remain on the west. The north-south crosswalk on the east side of Eglinton Avenue will remain closed, and the crosswalk on the west side of Eglinton Avenue will be open. The traffic flip will begin as early as 5 a.m. and take approximately two (2) hours to complete. Lire la suite »

septembre 132019

Emergency Weekend and Overnight Bell Work at Mount Pleasant Station Friday, September 13, 2019

What Work is Taking Place?

Starting Friday September 13, crews will work through the weekend and overnight to perform emergency Bell utility work on the south side of Eglinton Ave E. Construction activities include excavation and cable repair work. This work requires the use of excavators, hydro-vacuum trucks and generators, as well as site lighting. This work will take place within the existing work zone. Crews will endeavour to minimize disruption as much as possible. Lire la suite »

septembre 112019

Extension of the Secondary Entrance Work Zone Friday September 13, 2019

As early as Friday September 13, the secondary entrance work zone will be extended eastward, approximately three (3) metres from 300 Eglinton Avenue E to accommodate ongoing construction activities at Mount Pleasant Station. All protection barriers and fences surrounding the work zone will be maintained. This configuration will be in place until approximately late October 2020. Lire la suite »