Setup of Jet Grout Plant on Eglinton Avenue East between Dunfield Avenue and Redpath Avenue

SEE VIDEO

What work is starting?

What: Crews will setup a jet grout plant on the north side of the roadway on Eglinton Avenue East between Dunfield Avenue and Redpath Avenue. Lire la suite »

juin 252015

Toronto Hydro Utility Overhead Relocation Work at Mount Pleasant and Eglinton

What work is starting?

What: Toronto Hydro crews will relocate overhead Hydro utilities at the intersection of Mount Pleasant Road and Eglinton Avenue East ahead of headwall construction for the future Mount Pleasant Station.  Lire la suite »

juin 102015

What phase of work is coming in the vicinity of Mount Pleasant Road?

Utility Relocation: The first stage of work in this area is utility relocation. Construction of headwalls requires some utilities such as hydro, gas, water, telecommunication, etc.,to be moved safely out of the way in advance of tunnel and station construction. Lire la suite »

juin 102015

Utility Investigation and Relocation Work at Mount Pleasant and Eglinton

What work is starting?

What: Crews will be investigating and relocating utilities at the intersection of Mount Pleasant Road and Eglinton Avenue East prior to the construction of headwalls for the future Mount Pleasant Station.  Lire la suite »

mai 052015

Mount Pleasant Public School Meeting May 5

On Monday, May 4, Councillor Josh Matlow hosted a public meeting with the TDSB, parents of children attending Eglinton Junior Public School and Metrolinx to discuss station construction plans regarding the location of a vent shaft on school property, and general construction staging activities regarding the setup of a jet grout plant nearby. Lire la suite »

mars 162015

Monitoring Equipment Installation along Eglinton Avenue East

What: Monitoring equipment will be installed at major intersections along Eglinton Avenue East. This equipment will measure noise and vibration that may be related to the work of our tunnel boring machines underground. These measurements will allow construction crews to adjust tunnelling activities along Eglinton Avenue East if needed.   Lire la suite »

février 062015

Tree Removal and Protection in the vicinity of 440 Eglinton Avenue East

What work is starting?

What: Crews will be removing a tree, which is adjacent to Eglinton Avenue East in the vicinity of 440 Eglinton Avenue East. Lire la suite »

janvier 082015

2014 Year-in-Review

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with a 10-kilmetre underground tunnel in its central section. When it’s complete, the line will connect Mount Dennis in the west to Kennedy Road in the east, and will be up to 60% faster than bus service today. Lire la suite »

janvier 082015

Retour sur l’année 2014

Le projet Eglinton Crosstown est une ligne de transport léger sur rail (TLR) de 19 kilomètres qui longera Eglinton Avenue au cœur de Toronto et comprendra un tunnel souterrain de 10 kilomètres dans sa section centrale. Lorsqu’elle sera terminée, la ligne reliera Mount Dennis, à l’ouest, à Kennedy Road, à l’est, et offrira un service jusqu’à 60 % plus rapide que le service d’autobus actuel.  Lire la suite »

décembre 192014

Emergency Exit Building Construction Stage 1 – Utility Relocation Work on the North Side of Eglinton at Petman Avenue

What:  Crews will relocate underground utilities beneath the Eglinton Avenue roadway and in the vicinity of Petman Avenue. Lire la suite »