Mount Pleasant Dewatering to Commence Week of June 20, 2016

What work is starting?

What: Dewatering will commence to allow crews to perform scheduled maintenance on the tunnel boring machines. Dewatering wells were installed in advance of the arrival of the tunnel boring machines.  Lire la suite »

juin 152016

South Eglinton Avenue Sidewalk Restoration at Mount Pleasant Road

What work is starting?

What: Following the completion of headwall construction, crews will restore the sidewalk on the south side of Eglinton Avenue East.

Why: This restoration work is required to return the Mount Pleasant Road and Eglinton Avenue intersection to its original condition after headwall construction, completed in early 2016 for the future Mount Pleasant station.  Lire la suite »

juin 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

juin 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue. Lire la suite »

juin 032016

Disruption from service locomotives

Dear Neighbour, 

As you may know, the Eglinton Crosstown LRT Project includes a 10-kilometre underground portion. Two Tunnel Boring Machines (or “TBMs”) are building the 3.5km eastern underground section of the Crosstown tunnels between Brentcliffe Road and Yonge Street. The TBMs are making great progress tunneling at an average rate of over 10-15 metres per day.  They have completed approximately 70% of their journey and expected to be at Yonge Street in early September. Lire la suite »

mai 272016

Mount Pleasant Installation of Dewatering Wells June 2016

What work is starting?

What: Crews are required to install dewatering wells in advance of the arrival of the tunnel boring machines, Don and Humber. Following the installation, dewatering work will commence as early as late June 2016.

When: Starting as early as May 30, 2016 until late June 2016, construction will begin on the south side of Eglinton Avenue East, east of Mount Pleasant Road. Some work may be rescheduled or adjusted due to weather conditions and/or unforeseen circumstances. Lire la suite »

mai 112016

Roadway Restoration on Eglinton Avenue East and Mount Pleasant Road Continues

What phase of work is starting?

What: Crews are resuming road surface restoration in the vicinity of Mount Pleasant. This work is being done following the completion of the Mount Pleasant headwalls on the north side of Eglinton Avenue East.

Why:  Temporary pipes were installed underneath the Eglinton Avenue East roadway for station headwall construction. With the completion of this work these pipes will now been removed and the roadway will be restored.  Lire la suite »

avril 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Lire la suite »

février 262016

Demolition Work for Future Mount Pleasant Station

What work is starting?

In February 2016, crews began conducting preparatory activities and utilities works including surveying, locating utilities, and drilling boreholes to obtain additional information of sub-surface utilities and ground conditions in the Mount Pleasant Road and Eglinton Avenue East vicinity to make way for the future Mount Pleasant Station.

Upcoming Works – Demolition Lire la suite »