Mount Pleasant Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
septembre 292016

Subsurface Utility Engineering (SUE) Investigations Mount Pleasant Station

What Work is Taking Place?

  • To prepare for future construction of Mount Pleasant Station, crews will be conducting Subsurface Utility Engineering (SUE) investigations along Eglinton Avenue East and Mount Pleasant Road.
  • Crews will drill bore holes and use a hydro-vacuum truck within the roadway to determine the location of the underground utilities and the ground conditions around the intersection for design purposes. 
septembre 062016

Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Lire la suite »

août 152016

Update: Mount Pleasant Crosswalk Re-opened Demolition Work Continues

Update

As a response to community request, Metrolinx and its constructor, CTS, have redesigned the pedestrian crosswalk staging around the demolition site on the northwest corner of the Mount Pleasant Road and Eglinton Avenue East intersection. Pedestrians are now safe to use all crosswalks.

What work is Taking Place? Lire la suite »

juin 302016

Enbridge Gas Distribution Line Relocation for Mount Pleasant Station: Beginning July 2016

What Work is Taking Place?

  • Enbridge Gas Distribution (Enbridge) will be relocating natural gas pipelines at the site of the future Mount Pleasant Station. 

Timing

  • Work will start July 4, 2016 and will last for approximately 10 weeks.
  • Work will occur between 7:00 a.m. and 4:00 p.m, Monday to Friday.
  • Work could be rescheduled due to weather conditions or unforeseen circumstances

What to Expect Lire la suite »

juin 232016

Tunnelling: What You May Experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Lire la suite »

juin 222016

Mount Pleasant Dewatering to Commence Week of June 20, 2016

What work is starting?

What: Dewatering will commence to allow crews to perform scheduled maintenance on the tunnel boring machines. Dewatering wells were installed in advance of the arrival of the tunnel boring machines.  Lire la suite »

juin 152016

South Eglinton Avenue Sidewalk Restoration at Mount Pleasant Road

What work is starting?

What: Following the completion of headwall construction, crews will restore the sidewalk on the south side of Eglinton Avenue East.

Why: This restoration work is required to return the Mount Pleasant Road and Eglinton Avenue intersection to its original condition after headwall construction, completed in early 2016 for the future Mount Pleasant station.  Lire la suite »

juin 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

juin 132016

Road Restoration on Eglinton Avenue East, west of Mount Pleasant Road

What work is starting?

What: Following the completion of Mount Pleasant headwall work, road surface restoration is required on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue.

When: Starting approximately from Tuesday, June 14, 2016 until approximately Friday, June 17, 2016.

Where: Crews will be working in the middle lanes on Eglinton Avenue East, west of Mount Pleasant Road to Brownlow Avenue. Lire la suite »