Overnight Utility Inspection at Weston Road and Eglinton Avenue West - March 31 & April 1, 2021

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

 
mars 30, 2021

 

What Work is Taking Place?

Crews at Mount Dennis and the Rail Corridor continue with utility inspections. On Wednesday March 31 and Thursday April 1, crews will be inspecting the existing utilities overnight from 10:00pm - 6:00am. A new workzone will be erected west of Weston Rd. Access to surrounding properties will remain open, and traffic will be controlled by traffic control personnel and Paid Duty Officers. All current traffic restrictions at the intersection will remain in place.

 

What to Expect

Crews will be performing a CCTV inspection of the existing maintenance holes. A new workzone will be erected on Eglinton Ave W, west of Weston Rd. Around the workzone, one lane travelling eastbound will be maintained. Access to businesses and residences will be maintained.

 

HOURS OF WORK

  • Wednesday March 31 and Thursday April 1
  • Crews will be working from as early as 10:00pm to 6:00am  
  • Work may be rescheduled due to weather conditions or unforeseen circumstances
  • The contractor may not always work during the permitted hours but may do so at its discretion
  • This work may take longer or shorter than expected

 

TRAFFIC DETAILS

  • All turns at Weston Rd and Eglinton Ave W will remain open
  • Access to Weston Rd and Eglinton Ave W will be maintained

 

PEDESTRIAN DETAILS

  • All current pedestrian restrictions will remain in place
  • Access to businesses and properties will be maintained