Sidewalk Closure between Pharmacy and Lebovic for Civil Road Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue.

There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work, beginning as early as Monday February 18, 2019 for approximately one (1) month. Lire la suite »

février 052019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Lire la suite »

janvier 182019

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road.

Telecom work has been extended until the Spring 2019.

Lire la suite »

janvier 152019

Duct Bank Concrete Pour of Guideway Between Eglinton Square to Pharmacy Avenue

Last Updated: January 24, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Lire la suite »

novembre 222018

Eastern Works Open House (O’Connor Stop to Kennedy Station)

Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 202018

Nightly Crosswalk Closure at Pharmacy Avenue and Eglinton to Facilitate Watermain Installation

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be closing the east side crosswalk (north-south) at Pharmacy Avenue and Eglinton Avenue East intersection as early as Monday, November 19, 2018 for approximately four (4) nights. Lire la suite »

novembre 162018

Crosswalk Closure at Pharmacy Avenue and Eglinton Avenue East to Facilitate Catch Basin Installation

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be closing the west side crosswalk (north-south) at Pharmacy Avenue and Eglinton Avenue East intersection as early as Monday, November 19, 2018 for approximately five (5) weeks.

The closure is required to provide safe and adequate space for catch basin installation and boulevard work. Lire la suite »

novembre 142018

Guideway Work along Surface Section of the Eglinton Crosstown LRT: Victoria Park Avenue to Pharmacy Avenue

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting guideway work in the center of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue starting as early as November 24, 2018 until early 2019. The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.

Stage 2: Lire la suite »

novembre 082018

Extended: Rolling Sidewalk Closures for Civil Road Work from Victoria Park Avenue to Pharmacy Avenue

What Work is Taking Place?

In support of construction of the future At Grade stops, crews continue civil works in relation to road widening works on both the north and south sides of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue. Work began in mid-September 2018.

Work has been extended until Friday, November 30, 2018. Lire la suite »

novembre 062018

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

Crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road, as part of construction of the future surface section for the Eglinton Crosstown LRT.

Telecom work commenced in February and has been extended until the end of the year (Fall/Winter 2018).