Guideway Work at Warden Avenue

What Work is Taking Place?

As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at Warden intersection at Eglinton Avenue East. As early as July 29, 2019 the construction zone will shift to the center of Eglinton Avenue East at Warden Avenue and be in place for approximately six (6) weeks. There will be no through north-south traffic on Warden and left turn restrictions at the intersection. Lire la suite »

juillet 052019

UPDATED: Duct Bank installation at Warden Avenue for TPSS 11

What Work Is Taking Place?

Work on the southeast corner of Warden Ave and Eglinton Ave E will start as early as July 8th, 2019 to support the upcoming construction of Traction Power Substation (TPSS) 11 that will power the Eglinton Crosstown Light Rail Transit (ECLRT) line.

This work will be ongoing until the end of July 2019.

Crews will continue excavating, installing, and pouring concrete for duct banks at the south east corner of the Warden intersection. Lire la suite »

juin 252019

Updated: Duct Bank Installation at Warden Avenue for Traction Power Substation (TPSS) 11

Originally Posted: April 12, 2019 

Updated: June 25, 2019 

What Work is Taking Place? Lire la suite »

mai 282019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on May 28, 2019. You can see the presentation here:

Lire la suite »

mai 152019

Concrete Pour of Guideway - East of Warden Avenue May 16 and May 17, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East, just east of Warden Avenue and Thermos/Sinnott Road. Lire la suite »

mai 132019

Construction Begins for Traction Power Substation 11

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be commencing construction of the Traction Power Substation (TPSS) 11 that will power the Eglinton Crosstown Light Rail Transit (ECLRT). The work will take place in the work zone on the south east side of Warden Avenue in close proximity to 795 Warden Avenue Lire la suite »

mai 102019

Track Slab Concrete Pour of Guideway- Eglinton Square

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. 

Crews will be delivering and pouring cement along Eglinton Avenue East between Eglinton Square and Pharmacy Avenue as early as Wednesday May 15 from 7:00 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East. Lire la suite »

avril 302019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:

Lire la suite »

avril 182019

Updated: Concrete Pour of Guideway - East of Warden Avenue - April 22 & April 24, 2019

Originally Posted: April 15, 2019

Updated: April 18, 2019 

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East, just east of Warden Avenue and Thermos/Sinnott Road. Lire la suite »

avril 112019

Eastern Works Open House

Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here: