(Updated) Glazing Installation at Golden Mile, Birchmount, O'Connor and Wynford Stops

UPDATED OCTOBER 23, 2020

What Work is Taking Place?

Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters.  Glazing consists of glass Installation works for the LRT shelters.

What to Expect Lire la suite »

octobre 012020

Duct Bank Installation at The West Don River Bridge

What Work is Taking Place?

Crews will begin installing duct banks under the West Don River Bridge as early as October 5, 2020. To perform this work safely, an alternating lane closure under the bridge will be in place for approximately six (6) weeks. Access to the E.T Seaton Park parking lot, south of Eglinton Avenue East will be maintained. There will be no impacts to traffic on Eglinton Avenue East.

août 122020

Late Night Concrete Pours at Wynford Drive and Victoria Park Avenue

What Work is Taking Place?

Starting August 2020, crews will perform late night concrete pours between Wynford Drive and the East Don River Bridge, and between Jonesville Crescent and Victoria Park Avenue. The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.  Late night pours will occur twice per week, starting as early as Thursday August 13, 2020, for approximately six (6) weeks. Pours will take place between the hours of 10:00 p.m. – 3:00 a.m. Crews will endeavour to minimize disruption as much as possible. Lire la suite »

Catégories:
juillet 172020

Sidewalk, Curb and Roadworks Construction

 

What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be constructing new sidewalks and curbs and performing final roadworks on the north side of Eglinton Avenue East, west of Swift Drive. Work is expected to begin as early as July 20, 2020 and last for a period of three (3) weeks.

Work Area Map

Lire la suite »

Catégories:
juillet 162020

SHELTER INSTALLATION AT WYNFORD STOP July 20, 2020

 

Hours of Work
• Shelter installation will begin as early as July 20, 2020 for approximately one week.
• Work may be performed between the hours of 7:00 a.m. and 11:00 p.m.
• Work may be rescheduled due to weather conditions or unforeseen circumstances.

Work Area Map
  Lire la suite »

Catégories:
juillet 152020

SHELTER INSTALLATION AT WYNFORD STOP, July 15, 2020

What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Lire la suite »

Catégories:
juillet 152020

Shelter Installation at Wynford Stop North Platform - July 15, 2020

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Wynford Stop north platform. Installation will begin as early as July 15, 2020 for approximately three (3) days. Lane closures will be required for this work.  Lire la suite »