Cross Passage Construction east of Old Park Road

 
février 29, 2016

 

 

    Cross Passage Construction east of Old Park Road

 

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today. 

 

What:  

A cross passage is a small passageway built to connect the eastbound and westbound tunnels for maintenance and emergency purposes. Dewatering equipment is used at street level on Eglinton Avenue above the cross passage location. Dewatering is the process of removing groundwater from around the tunnel level below. The dewatering equipment will be in place for the duration of the building of the cross passage.

 

3 stages of cross passage work:   

 

Stage 1: Drilling 

Drilling of the dewatering wells in the centre lanes of Eglinton Avenue and cutting a small trench to the north curb lane (approximately one month.)

 

Stage 2: Dewatering 

Placing a generator and a dewatering treatment tank on north side of Eglinton Avenue, requiring a short curb lane restriction (approximately six months).

 

Stage 3: Restoration 

Removal of the equipment/wells and restoration of the roadway once the cross passage work is complete

(approximately one month.)

 

Where:  

While the majority of work will occur underground within the tunnels, dewatering operations will be visible on the surface on Eglinton Avenue between Glen Cedar Road and Camberwell Road. The highlighted areas on the maps show the approximate location of the cross passage work. 

 

When:  

Work will begin as early as the first week of March and last approximately eight monthsTimelines may be rescheduled or adjusted due to weather conditions and unforeseen circumstances.

 

Traffic Details:  

 

During Stage 1, traffic will be reduced to one lane in each direction while the work will occur in the centre lanes. During this stage, parking on Eglinton will be prohibited and used for the flow of traffic. Delays should be expected.

 

Setup during the first phase of construction.

 

During Stage 2, westbound traffic will be impacted with the north curb lane restriction only. A few parking spots will be occupied by the dewatering equipment at this location.


Setup during second phase of construction

 

 

Transit Information

For the safety of transit riders, eastbound or westbound TTC bus stops in the affected area will be relocated.  The eastbound bus stop at Old Park is to be maintained. Watch for posted signs and future information indicating the new locations. 

 

Work Hours

Please note that dewatering pumps and or generators are required to be active 24 hours a day.

 

Noise and Vibration

Some noise and vibration associated with the equipment can be expected with this work.

 

Please Contact Us

If you would like more detail about this work or any other aspect of the Eglinton Crosstown, please contact us. We thank you for your continued patience as we work to complete this important project.

 

Carlos Hernandez

West Community Office

1848 Eglinton Avenue West

416-782-8118

crosstown@metrolinx.com  

www.thecrosstown.ca

 

 

Please support your local businesses during construction