Concrete Pour at Caledonia Station March 2, 2020

 
mars 2, 2020

 

What Work is Taking Place?

On Monday, March 2, 2020, crews at Caledonia will be pouring concrete to form a slopped roof slab. The concrete pour will begin at 3:00am and continue to 5:00pm. No lane closures will be required for this work.

 

Hours of Work

  • Tuesday, March 3, 2020
  • The concrete pour will begin at approximately 3:00am and last for approximately fourteen (14) hours.

The contractor may not always work during permitted hours but may do so at its discretion.

  • Work may be rescheduled due to weather conditions or unforeseen circumstances.
  • This work may be longer or shorter than expected.  

What to Expect

  • Concrete trucks will be entering and exiting the work zone.
  • Motorists can expect delays when travelling through the intersection.
  • There will be no impacts to pedestrian routes or TTC stops

 

Construction Staging Map

Concrete Pour Location

Stay Informed

Sign up for email updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton Corridor.

 

Disponible en français

 

For more information, please contact the West Community Office.

Thank you for your patience as we work to build this important project.

Please support your local businesses during construction.