Update: Cross Passage 10 at Eglinton Avenue East and Lillian Street

 
avril 7, 2020

 

What Work is Taking Place?

Excavation of the cross passage at Eglinton Avenue East and Lillian Street is complete. The north and south tunnels are now connected, allowing the next phase of construction to begin. 

Crews will start permanent works within the cross passage, forming the final structure of the corridor since mid-March. Permanent works, including rebar installation, waterproofing, and concrete pours, will take approximately four (4) months to complete. Work will take place on a 24-hour basis. 

The dewatering system, located on the south-east corner of Lillian Street, will continue to operate on a 24-hour basis, until the permanent works are complete. The second generator will remain in place as a backup. The generators will not operate at the same time.

Periodic dewatering and monitoring maintenance will continue along Eglinton Avenue East, Monday to Friday between 9:00 a.m. – 4:00 p.m.

 

Hours of Work

Mid-March 2020 for approximately four (4) months.

Work will take place on a 24-hour basis 

Maintenance work will take place Monday - Friday between 9:00 a.m. - 4:00 p.m. 

Work may be delayed or rescheduled due to inclement weather or unforeseen circumstances.

 

Work Area Map

 

What to Expect

Noise from pumps, generators, and other construction equipment. 

Storage of materials and equipment within the preexisting work zones. 

 

Traffic and Pedestrian Changes

All pedestrian and traffic routes will remain the same. 

Periodic lane reductions for maintenance works.  

 

Transit Information

Access to TTC will be maintained at all times.

Visit www.ttc.ca for more information

 

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.

 

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

 

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.

 

Disponible en français