Update: Extended Construction Hours at Mount Pleasant Station - Phase Three: Concrete Works

 
juin 12, 2020

 

What Work is Taking Place?

Starting in mid-June 2020, crews will begin concrete works, the third phase of extended construction at Mount Pleasant Station. Concrete pours will take place at the station entrances and beneath Eglinton Avenue to form the final station structure underground. Structural steel framing, rebar, and formwork will be installed to reinforce the station’s concrete walls and slabs. Concrete pours are expected to take place on a weekly basis and each pour will take approximately 12 - 18 hours to complete. To ensure the integrity and continuity of the pour, work will begin as early as 5:00 a.m. A separate notice will be distributed in advance of each pour.  

 

Construction will take place on a 24-hour basis. Concrete works will continue through to early-2021. On-site mitigation measures will be in place to minimize disruption caused by this work. Deep excavation, tunnel demolition, and chipping will continue during this phase of construction, through to mid-Summer 2020. Crews will endeavour to perform noisier work, such as chipping and drilling, between 6:00 a.m. and midnight. Please carefully review ‘What to Expect’ for more information.

 

Hours of Work

Construction will take place on 24-hour basis, Monday through Sunday

Concrete pours will take place weekly for approximately 12 - 18 hours.

Large volume concrete pours will begin as early as 5:00 a.m.

Crews may not work every night, and work may be delayed or rescheduled due to inclement weather or unforeseen circumstances

 

Work Area Map

What to Expect

Overnight noise from construction activity, including trucks, chipping of concrete, generators and heavy equipment.

Construction lighting is required; lighting will be positioned away from residential properties.

Periodic lane reductions for utility work.

Several trucks entering/exiting the site every hour, as well as truck staging around work zones.

Concrete trucks will stage on Eglinton Avenue East, Mount Pleasant Road, and within the work zones. 

 

Pedestrian and Traffic Changes

All pedestrian and traffic routes at Mount Pleasant Station are expected to remain the same.

Trucks will enter and exit through the main and secondary entrances.

 

Transit Information 

Access to TTC will be maintained at all times. 

Please visit www.ttc.ca for more information.

 

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.

 

Stay Informed

Sign up for e-mail updates at www.thecrosstown.ca/sign-up or download the Crosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.

 

Thank you for your continued patience as we work to build this important project.

Please support your local businesses during construction.