UPDATED: Sidewalk Restoration Works at Caledonia Station - Monday, June 20, 2022

 
juin 30, 2022

 

What Work is Taking Place?

As early as, Monday, June 20, 2022, crews at Caledonia Station will be performing sidewalk restoration works on the north side of Eglinton Avenue West between Blackthorne Avenue and Croham Road. To facilitate this work, the sidewalk on the north side of Eglinton Avenue West between Blackthorne Avenue and Croham Road will be temporarily closed. Pedestrians will be safely rerouted around the work zone. Westbound traffic on Eglinton Avenue West will be reduced to two lanes east of Blackthorne Avenue. This works is expected to take place on Monday – Friday between 7:00 a.m. to 5:00 p.m. for approximately three (3) weeks.

 

What to Expect

Noise from construction activities, including concrete breaking and pouring, can be expected.  Expect delays while travelling through the area. The sidewalk will reopen upon completion of the work.

 

HOURS OF WORK

  • As early as Monday, June 20, 2022, for approximately three (3) weeks.
  • This work is expected to take place on Monday – Friday between 7:00 a.m. to 5:00 p.m.
  • Work may be rescheduled due to inclement weather and/or unforeseen circumstances.
  • This work may be longer or shorter than expected.

 

TRAFFIC DETAILS

  • Westbound traffic on Eglinton Avenue West will be reduced to two lanes east of Blackthorne Avenue.

 

PEDESTRIAN DETAILS

  • The sidewalk on the north side of Eglinton Avenue West will be temporarily closed between Blackthorne Avenue and Croham Road.
  • Pedestrians will be safely rerouted around the work zone.

 

TRANSIT INFORMATION

  • The westbound TTC bus stop located at Blackthorne Avenue will be temporarily relocated approximately 10-metres east.
  • Please visit www.ttc.ca for more information.