TTC Line 1 Closures for Eglinton Crosstown LRT Construction Work (July 23 - July 24, 2022)

 
juillet 19, 2022

 

What Work Is Taking Place?

TTC’s Line 1 subway will be closed between Sheppard-Yonge and St. Clair stations from Saturday, July 23 – Sunday, July 24, 2022, to facilitate construction activities for the Eglinton Crosstown LRT, including platform extension and mechanical electrical works. Work will take place on a 24-hour basis from Saturday, July 23 – Sunday, July 24, 2022. Berwick Avenue will remain open while this work takes place.

What to Expect

Noise from construction activity, including trucks. All work zones at Yonge Street and Eglinton Avenue will remain in place. Property access will be maintained. 

HOURS OF WORK

  • Saturday, July 23 – Sunday, July 24, 2022.
  • Crews will work 24 hours during the subway closure.
  • This work may be delayed or rescheduled due to inclement weather or unforeseen circumstances. 

TRAFFIC AND PEDESTRIAN DETAILS

  • No changes to the current traffic configuration and pedestrian routes are expected, as a result of this work.

TRANSIT INFORMATION

  • TTC Line 1 subway will be closed from Saturday, July 23 – Sunday, July 24, 2022, between Sheppard-Yonge and St. Clair Stations. 
  • Please visit TTC’s website www.ttc.ca, under “Service Advisories” for more information on subway closures and shuttle bus operation.

Disponible en français.