What's New?

 
Syndicate content
 
April 13 2021

Cedarvale & Forest Hill Construction Update - March 31, 2021

The following construction update for Cedarvale and Forest Hill stations has been updated as recently as March 31, 2021. You can view the presentation here:

Read more »

April 08 2021

Upcoming Concrete Pour at Bayview Avenue and Eglinton Avenue East

 

Traffic Configuration

As early as Wednesday April 14, 2021 crews at Leaside Station will perform a concrete pour at the Main Entrance site. The concrete will form the roof of Leaside Station’s Main Entrance building. 

  Read more »

April 07 2021

Tower Crane Removal at Kennedy Station April 7, 2021

 

What Work is Taking Place?

As part of the construction of the future Kennedy Station, crews will be removing a tower crane within the construction zone at Kennedy Station, south of Eglinton Avenue East.

 

What to Expect

April 07 2021

Notice of Water Shut-off at Fairbank Station - Friday April 9, 2021

 

What Work Is Taking Place?

On Friday April 9, 2021, crews will perform investigative watermain work on Eglinton Avenue West, east of Dufferin Street.  A water shut-off is required to facilitate the work.  Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

 

Water Shut-off Details: Read more »

April 06 2021

Concrete Pour at Fairbank Station - Wednesday April 7, 2021

 

What Work is Taking Place?

Crews at Fairbank Station continue to perform large concrete pours. Crews will be pouring on Wednesday April 7, beginning as early as 7:00 a.m. Concrete pumps will be placed within the Main Entrance work zone. Concrete trucks will be staged on Dufferin Street, south of Eglinton Avenue West. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.

April 06 2021

Update: Crane Mobilization on Berwick Avenue

Traffic Configuration

 

As early as Friday April 9, 2021, crews at Eglinton Station will resume pre-cast panel installations at the Berwick Portal site. To facilitate this work, use of a mobile crane will be required at the Berwick Portal until approximately Friday, April 16, 2021. 

  Read more »

April 02 2021

Utility Crossing Work and Track Resurfacing at Kennedy Station's GO Corridor April 2-4, 2021

What Work is Taking Place?

Crews at Kennedy Station continue with GO corridor development, including utility installations. From Friday April 2 until Sunday April 4, crews will be installing utility casing crossings within the GO track area, followed by track resurfacing. Crews will be working from as early as 6:00am until 11:00pm.

 

What to Expect