Cross Passage Headwall Construction for Twin Tunnels Stage 2 – Southside Switch

What we are building

What:  A cross passage is a smaller tunnel placed between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the cross-passage required for future maintenance of the tunnels. Headwalls are underground support walls. Read more »

August 052014

Short Term Lane Closures along Eglinton Avenue West for Monitoring Equipment Installation Black Creek Drive -Yonge Street Summer 2014 - Summer 2015

What work is starting?

What: Crews will be installing ground movement monitoring equipment.
 
Why: Monitoring equipment will provide information on the ground conditions during excavation and tunnelling activities to the construction team. Read more »

July 182014

Update: Cross Passage Headwall Construction near Vesta Drive - Stage 1

What we are building

What: A cross passage is a tunnel cut between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the future cross-passage required for future maintenance of the tunnels. Read more »