November 172014

Cross Passage Construction Update – November 2014

Information as of November 5, 2014

What is the Crosstown?

The Eglinton Crosstown is a 19-kilometre light rail transit (LRT) line that will run along Eglinton Avenue through the heart of Toronto, with an underground central section. The line will connect Mount Dennis in the west to Kennedy Road in the east, and the new service will be up to 60% faster than the bus service today. 

Did you know? Read more »

October 222014

Bathurst Station Headwall Construction for Twin Tunnels

What we are building

What: Crews will be building headwalls for the future Bathurst Station. Headwalls are underground support walls located at the east and west ends of the underground station. Following the site preparation, crews will be installing these underground station headwalls in advance of the twin tunnel construction.
  Read more »

October 152014

Cross Passage Headwall Construction for Twin Tunnels Stage 2 – Southside Switch - UPDATE

What we are building

What: A cross passage is a smaller tunnel placed between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the cross-passage required for future maintenance of the tunnels. Headwalls are underground support walls. Read more »

September 032014

Open houses in September

Metrolinx is hosting three open houses in September at various locations along the Eglinton corridor to provide an update on current Crosstown construction.

Join us at one of the following sessions to hear what is happening, why it needs to happen and how it may impact you:

Tuesday, September 9, 2014

7:00 - 9:00 pm Read more »

August 282014

Long-term Closure of Peveril Hill North at Eglinton Avenue West

What we are building

What:  Construction of the headwalls for the future Bathurst station requires a small grout plant to be established nearby to pump a form of concrete, otherwise known as “grout”, to the station headwall location. In order to minimize road occupancy on Eglinton Avenue West this grout plant will be located within a section on Peveril Hill North, south of Eglinton. Some road adjustments will take place to accommodate the grout plant. Read more »

August 252014

Cross Passage Headwall Construction for Twin Tunnels Stage 2 – Southside Switch

What we are building

What:  A cross passage is a smaller tunnel placed between two other parallel tunnels for maintenance or emergency purposes. Crews will be building one headwall for the cross-passage required for future maintenance of the tunnels. Headwalls are underground support walls. Read more »