January 232017

Update: Bell Utility Relocations at Leaside Station

What Work is Taking Place?

To complete the Bell Relocations works currently underway at the Bayview and Eglinton Avenue East intersection, crews will extend the work zone in to the intersection at Bayview Avenue on the south side of Eglinton Ave E. Work will take place in two stages; stage one will take place on the west side of Bayview Avenue at Eglinton Avenue and stage two will take place in the middle of Bayview Avenue at Eglinton Avenue. Read more »

January 132017

Bell Utility Relocations at Leaside Station

What Work is Taking Place?

To complete the Bell Relocation works currently underway on the southwest corner of Bayview Avenue and Eglinton Avenue East, crews will extend the work zone into the intersection on the south side of Eglinton Ave East.

Stage 2 for Bell Utility Relocations

Timing Read more »

December 192016

Shoring at Leaside Station

What Work is Taking Place?

Beginning in early-January 2017, and pending permit approval, crews will start support of excavation work, also known as shoring, at the future Leaside Station. The station is located at the intersection of Bayview Avenue and Eglinton Avenue East, with the main station entrance on the southeast corner and the secondary entrance on the northwest corner. Steel piles as well as braces and tie-backs will be installed around the perimeter of the station box and entrances to support excavation.  Read more »

December 092016

Update: Maintenance Work at Cross Passage 11

What work is Taking Place? 

Crews will perform maintenance on the dewatering wells for Cross Passage 11.  Dewatering wells are required for cross passage construction to ensure that the water table remains low enough to allow for hand mining work to be completed.

Hours of Work Read more »

November 282016

One Day Road Closure: Roehampton Avenue

What Work is Taking Place?

A large crane is required to replace hydro poles on the east end of Roehampton Avenue. Safe crane operation near hydro lines necessitates the road closure.

Timing Read more »

October 242016

Overhead Hydro Work Continues for Leaside Station

What Work is Happening?

Since September 2016, crews have been completing overhead hydro relocations around the Bayview Avenue and Eglinton Avenue intersection. As early as the week of October 24, crews will be replacing overhead wires and anchors on the south side of Eglinton Avenue East at Bessborough Drive.

Impacts for School Read more »

October 202016

Telecom Relocation for Leaside Station

What Work is Taking Place?

Crews will relocate existing telecommunications utilities from overhead to underground around the Eglinton Avenue and Bayview Avenue intersection. For the safety of the public and workers, temporary pedestrian and traffic changes will be in effect to accommodate this work. Read more »