Bayview Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
April 192018

UPDATE: Pedestrian Route Changes at Leaside Station

ORIGINAL POST: APRIL 6, 2018

RE-ISSUE DATE: APRIL 19, 2018

 

WHAT WORK IS TAKING PLACE? Read more »

April 122018

Leaside & Laird Construction Liason Committee Meeting

The construction liaison committee meeting of Leaside and Laird was held on April 11, 2018. You can see the presentation here:

Download the presentation

April 112018

Lane Impacts Leaside Station

WHAT WORK IS TAKING PLACE?

Work requiring the temporary closure of the southbound lane, just south of Eglinton Avenue East will occur over the next week. Southbound traffic will be maintained by removing the northbound dedicated left turn lane. 

 

TIMING 

  Read more »

April 062018

Pedestrian Route Changes Leaside Station

WHAT WORK IS TAKING PLACE?

Over the next month, crews will complete right of way works including restoration of curbs and sidewalks on the south side of Eglinton Avenue both east and west of Bayview Avenue. This will result in some periodic changes to pedestrian circulation. Please watch for orange and black signage that directs pedestrians.

These works are required to support the completion of decking and restoration of the work zone to allow crews to shift to working on the north side of Eglinton Avenue in May 2018.

  Read more »

March 222018

Central Open House (Chaplin Station to Leaside Station)

Thank you for attending the open house about Chaplin Station to Leaside Station on March 21, 2018.

For those of you who missed it, the presentation is here: Read more »

March 162018

Lane Impacts and Driveway Work at Leaside Station

WHAT WORK IS TAKING PLACE?

Work requiring the use of the eastbound lane between Bayview Avenue and 1750 Bayview Driveway will continue for the next one (1) to two (2) weeks. This work is required to support the completion of decking on the southwest corner.

Read more »

March 152018

Leaside & Laird Stations Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on March 14, 2018. You can see the presentation here:

Read more »

March 062018

Sidewalk Repairs at Leaside Station on March 7

WHAT WORK IS TAKING PLACE?

On Wednesday, March 7 Leaside station crews will complete repairs on a section of sidewalk on the north side of Eglinton Avenue between Bayview Avenue and the Metro driveway. 

 Read more »

March 022018

Sidewalk Repairs at Leaside Station

WHAT WORK IS TAKING PLACE?

On Monday, March 5th Leaside station crews will complete repairs on a section of sidewalk on the north side of Eglinton Avenue between Bayview Avenue and the Metro driveway. 

 Read more »

February 232018

Overnight Line Re-Painting at Leaside Station

WHAT WORK IS TAKING PLACE?

Leaside station crews will complete a refresh to the crosswalks and lines in and around the Bayview Avenue and Eglinton Avenue East intersection. Due to the volumes of traffic in the area and existing construction set up reducing available lanes, these works will be completed during the overnight period. 

TIMING  Read more »