October 122017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on October 11, 2017. You can see the presentation here: Read more »

September 142017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on September 13, 2017. You can see the presentation here:

Read more »

September 072017

Emergency Exit Shaft near Leaside Station: Tunnel Invert Concrete Pour

What Work is Taking Place?

To prepare for track system installation in the new LRT tunnels, concrete must be poured to form the foundation of the track. The emergency exit site in front of Leaside High School will be used as the access points to the tunnels.

Trucks will access the tunnel shaft from the construction site entrance near Bessborough Drive, pump concrete into a pipe, and drive the concrete down the tunnel to where it will be poured into place. Read more »

August 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Read more »

August 082017

Trailer Relocation at Leaside Station

What Work is Taking Place?

With the start of piling operations at the Secondary Entrance, site trailers currently in the Metro parking lot will be relocated to the Main Entrance site on the south east corner on the south end of the site. Two flatbed trucks will be on site to transport the trailers.

Timing Read more »

August 072017

UPDATE: Overnight Crosswalk Removal and Re-Painting at Leaside Station

What Work is Taking Place?

Leaside station is required to do a refresh to the existing crosswalk painting at the Bayview Ave and Eglinton Ave E intersection. Due to the volumes of traffic in the area and existing construction set up reducing available lanes, these works will be completed overnight.  Read more »

July 192017

UPDATE: Support of Excavation Works at Leaside Station

What Work is Taking Place?

In early 2017, crews began drilling at the Main Station Entrance site as part of the support of excavation work, also known as shoring.  Drill work in the main station area has been completed. The drill machine will now be moved to the Secondary entrance site on the north west corner of Bayview Avenue and Eglinton Avenue East. Read more »

July 132017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on July 12, 2017. You can see the presentation here:

Read more »

July 102017

Water Main Investigations at Leaside Station

What Work is Taking Place

Crews will expose the portions of a water main on the north east corner of the Bayview Avenue and Eglinton Avenue East intersection. 