Birchmount Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
February 082021

Overnight Utility Inspection at Rosemount Dr and Eglinton Ave E

 

What Work is Taking Place?

Crews at Rosemount Drive and Eglinton Avenue East continue with utility activities. Overnight on Monday February 8, crews will be inspecting the existing utilities in the area, from as early as 11:30pm until 5:00am on Tuesday February 9. All current traffic restrictions at the intersection will remain in place.

 

December 232020

UPDATE: Closure on Rosemount Drive North of Eglinton Avenue East

Update: Reopening December 21, 2020 – January 11, 2021

What Work is Taking Place?

October 292020

Overnight OCS Cable Works on Eglinton Ave between Birchmount Road and Ionview Road - November 4-5, 2020

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Birchmount Road and Ionview Road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles).  Installation will take place overnight November 4-5, 2020 between the hours of 9:00 p.m. and 6:00 a.m.

 

What to Expect Read more »

October 222020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late December 2020

 

 

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late December 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work.

 

What to Expect Read more »

October 082020

(Updated) Glazing Installation at Golden Mile, Birchmount, O'Connor and Wynford Stops

UPDATED OCTOBER 23, 2020

What Work is Taking Place?

Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters.  Glazing consists of glass Installation works for the LRT shelters.

What to Expect Read more »