Birchmount Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
December 042018

Investigation of Underground Utilities between Birchmount Road and Rosemount Drive

What Work is Taking Place?

In support of construction of the future At-Grade stops, crews will be conducting subsurface utility engineering (SUE) investigation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive.

Crews will drill bore holes and use a hydro-vacuum truck within the City’s right-of-way and roadway to determine the location and depth of existing underground utilities for design purposes. Read more »

November 302018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Birchmount Road to Rosemount Drive

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting wet utilities relocation work along Eglinton Avenue East between Birchmount Road and Rosemount Drive. Starting as early as December 3, 2018 and lasting approximately four (4) months, crews will install new pipes, and replace manholes and catch basins. The work will be conducted in stages.

Stage 1 Read more »

November 222018

Eastern Works Open House (O’Connor Stop to Kennedy Station)

Thank you for attending the open house about Kennedy Station and O'Connor Stop to Ionview Stop on November 21, 2018. For those of you who missed it, the presentation is here:

Read more »

November 142018

Boulevard Restoration Work Between Warden Avenue and Birchmount Road

Originally Published: November 14, 2018

Last Updated: November 29, 2018

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting boulevard restoration civil work including road widening along Eglinton Avenue East between Warden Avenue and Birchmount Road. Read more »

November 062018

Extended: Telecommunication Relocation Work between Victoria Park Avenue and Birchmount Road

What Work is Taking Place?

Crews will continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road, as part of construction of the future surface section for the Eglinton Crosstown LRT.

Telecom work commenced in February and has been extended until the end of the year (Fall/Winter 2018).

Read more »

October 312018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on October 30, 2018. You can see the presentation here:

Read more »

September 252018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting wet utilities relocation work along Eglinton Avenue East between Warden Avenue and Birchmount Road. Read more »

September 252018

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 25, 2018. You can see the presentation here:

Read more »

September 172018

Update: New Traffic Changes from Victoria Park Avenue to Birchmount Road to Support Surface Section Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting traffic changes in order to accommodate road widening, upgrading and relocating wet utilities and dry utilities along Victoria Park Avenue to Birchmount Road starting as early as Friday, September 21st.

Preparatory work for the reconfiguration will take place as early as Friday, September 21, 2018 starting at 7:00 PM and ending Monday, September 24, 2018 at 6:00 AM. Read more »

September 142018

New Traffic Changes from Victoria Park Avenue to Birchmount Road to Support Surface Section Work

Originally Published: September 14, 2018

Updated: September 17, 2018

As work intensifies along the surface portion of the Eglinton Crosstown Light Rail Transit Project in preparation for guideway construction, there will be some major changes.

Expect to see new traffic changes between Victoria Park and Birchmount beginning less than a week from today — as early as Friday, September 21, 2018. Read more »