Pedestrian Safety near Construction Sites

Construction of the Eglinton Crosstown LRT line, including 15 underground stations, is underway. Since the end of school, many construction sites have been set up for station construction and the set-up of some major intersections along Eglinton Avenue has been changed.

Pedestrian Information Read more »

May 272016

Mount Dennis Station Open House

Thank you for attending our Mount Dennis station open house on May 26, 2016. 

For those of you who missed it, the presentation is here:

April 072016

Tunnelling: What you may experience

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive. For the tunnelled portion, locomotives run along interim track and transport materials and haul spoils in and out of the tunnels to the extraction shafts. Tunnel boring machines (TBMs) and muck removal operations run around the clock - 24 hours a day. Read more »

February 052016

Photography Drive Bridge Demolition

What is happening?

The first step in the construction of the Mount Dennis Station requires the demolition of the Photography Drive Bridge deck, which was closed in 2002. The Photography Drive Bridge is located over Eglinton Avenue West between Black Creek Drive and Weston Road. Eglinton will be closed between these streets during the demolition.

How: Read more »

February 012016

Tunnelling: What you may experience

Dear Neighbour:

As you may know, the Eglinton Crosstown includes a 10-kilometre underground portion, between Keele Street and Laird Drive.For the tunnelled portion, we have tunnel boring machines (TBMs) operating around the clock - 24 hours a day, seven days week.

On average, the tunnel boring machines each travel approximately 10-15 metres per day. TBMs are working approximately 16-20 metres below ground, but we sometimes hear from nearby residents who may experience noise and vibration from the TBMs as they pass through the area. Read more »

January 192016

Eglinton Crosstown Year-In-Review

The Crosstown team appreciates the patience of our neighbours and local businesses while we work to build new rapid transit. In 2015, the project made significant progress and hit a number of key milestones. We would like to take this opportunity to reflect on the past year and provide a look ahead to how we expect the project to progress in 2016. Read more »