Caledonia Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
September 082020

Lane Reduction for Escalator Delivery at Caledonia Station - September 9, 2020

 

What Work is Taking Place?

On Wednesday September 9, the final large escalators will be delivered to Caledonia station. During this activity, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:00am and last for approximately 12 hours.

 

What to Expect

August 312020

Lane Reduction for Escalator Delivery at Caledonia Station- September 3, 2020

What Work is Taking Place?

On Thursday September 3, a large escalator delivery will take place at Caledonia station. During this activity, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:00am and last for approximately 12 hours.

What to Expect Read more »

August 282020

Lane Reduction for Concrete Pour at Caledonia Station- September 1, 2020

What Work is Taking Place?

On Tuesday September 1, crews at Caledonia will be pouring concrete to form a wall connecting to the stations roof. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 7:00am and last for approximately six hours.

What to Expect Read more »

August 262020

Lane Reduction for Site Maintenance at Caledonia Station August 27, 2020

WHAT WORK IS TAKING PLACE?

On Thursday August 27, crews at Caledonia will be using a vac-truck to clean the site's sediment tank. During this activity, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 7:00am and last for approximately four hours.

August 192020

Lane Reduction for Concrete Pour at Caledonia Station - August 20, 2020

What Work is Taking Place?

On Thursday August 20, crews at Caledonia will be pouring concrete to form a wall connecting to the stations roof. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:30am and last for approximately nine hours.

 

What to Expect

August 062020

Lane Reduction for Concrete Pour at Caledonia Station - August 7, 2020

What Work is Taking Place?

On Friday August 7, crews at Caledonia will be pouring concrete to form slabs and stairs within the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 6:00am and last for approximately 12 hours.

What to Expect

July 152020

Lane Reduction for U-Fill Pour at Caledonia Station July 16, 2020

What Work is Taking Place?

On Thursday July 16, crews at Caledonia will be pouring u-fill into the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 5:00am and last for approximately ten hours.

Hours of Work Read more »

July 142020

Lane Reduction for Concrete Pour at Caledonia Station July 15, 2020

What Work is Taking Place?

On Wednesday July 15, crews at Caledonia will be pouring concrete to form walls within the station box. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 1:00pm and last for approximately four hours.

Hours of Work Read more »