Chaplin Crescent

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
April 092018

Chaplin & Avenue Construction Liaison Committee Meeting - April 4, 2018

The Avenue & Chaplin Construction Liaison Committee Meeting was held on April 4, 2018.

You can see the presentation here: Read more »

March 232018

Upcoming Traffic Change and Shoring Update at Chaplin Station

WHAT WORK IS TAKING PLACE?

Chaplin Station construction continues with a variety of ongoing construction activities. Traffic changes are required in order to continue to upgrade existing/install new utilities, continue shoring activities on the north side of Eglinton, and begin shallow excavation on the north side of Eglinton.

The new construction staging and associated traffic changes will be implemented as early as late March 2018. Read more »

March 222018

Central Open House (Chaplin Station to Leaside Station)

Thank you for attending the open house about Chaplin Station to Leaside Station on March 21, 2018.

For those of you who missed it, the presentation is here: Read more »

March 122018

Shoring at Chaplin Station Main Entrance

WHAT WORK IS TAKING PLACE?

Support of excavation (or shoring) continues at Chaplin Station. At the Main Entrance site, located on the northeast corner of Chaplin and Eglinton, there are some piles that remain to be installed.

As early as Wednesday, March 14, crews will begin piling activities at the Main Entrance. The drill will cross Eglinton to the Main Entrance site as early as Monday, March 12.

TIMING  Read more »

March 082018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on March 7, 2018. You can see the presentation here: Read more »

February 282018

Special Pile Installation at Chaplin Station

WHAT WORK IS TAKING PLACE?

Crews are currently completing support of excavation (or shoring) on the north side of Eglinton. As part of this work, two special polymer piles (vertical steel beams) will be installed.  Special polymer piles are large in depth and size.  Therefore, a longer drilling and concrete pouring period is required. To ensure the structural integrity of each pile, once installation begins, it cannot be stopped. Read more »

February 132018

TRAFFIC CHANGES AT CHAPLIN STATION: Closure of Latimer Avenue at Eglinton & Western Eglinton-facing Shoppers Drug Mart Driveway

WHAT WORK IS TAKING PLACE?

The north work zone at Chaplin Station is being extended further east, closing Latimer Avenue and the western, Eglinton-facing driveway of Shoppers Drug Mart. 

This traffic change is required to provide improved traffic safety conditions as we continue support of excavation (or shoring) and will also make way for the next steps of shallow excavation and roof slab construction.

TIMING 

  Read more »

February 082018

Chaplin and Avenue Construction Liaison Committee Meeting

The construction liaison committee meeting of Chaplin and Avenue Stations was held on February 7, 2018. You can see the presentation here:

Download the presentation.

Read more »

January 242018

Traffic and Pedestrian Changes at Chaplin Station for Wet Utility Work

Original Issue Date: January 8, 2018
Updated: January 24, 2018 

WHAT WORK IS TAKING PLACE?

As early as January 26, new construction staging and traffic and pedestrian changes will be implemented at Chaplin Station.  The southwest work zone will be extended south onto Chaplin Cres and the southeast work zone will be made smaller.

Wet utilities work, including watermain, storm and sanitary sewer installation and relocation, as well as support of excavation activities will occur during this stage.   Read more »

January 182018

Temporary Driveway Alignment Change at 564 Eglinton Avenue West for Chaplin Station

WHAT WORK IS TAKING PLACE?

Beginning January 22, crews will be performing pile installation beside the driveway of 564 Eglinton Avenue West.  To make space for the crane pad, the alignment of the driveway on Eglinton Ave W will be shifted to the west for a period of one week.  Drivers may experience delays when entering and existing the driveway.  A flag person will be on site to assist with entry and egress.

TIMING  Read more »