Chaplin Crescent

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
July 032019
June 072019

Updated: Road Closures for Traffic Bridge Installation at Chaplin Station

 

Updated July 4, 2019

Update: Due to various unforseen circumstances the re-opening of Chaplin Cres will be on July 12th, 2019.


Read more »

June 042019

Weekend Road Closures at Chaplin Station - Extended June 7-10, 2019

Update: Weekend Road Closures at Chaplin Station - Extended

June 7 – 10, 2019

  Read more »

May 022019

Construction Notice: Overnight Hydro Utility Work at Chaplin Station

Overnight Hydro Utility Work at Chaplin Station

Week of May 5 – 10, 2019

Permit Number: 81015401

What Work is Taking Place? Read more »

April 252019

Construction Notice: Weekend Road Closures for Pile Installation at Chaplin Station May 2019

Weekend Road Closures for Pile Installation at Chaplin Station

May 2019

 (Update: May 2, 2019 - TTC#14 Glencarin Detour Map Added) Read more »

April 152019

Overnight Concrete Pour at Chaplin Station

Overnight Concrete Pour at Chaplin Station
Wednesday April 17, 2019


On Wednesday April 17, 2019, at 2:00 a.m., crews will perform a large concrete pour.  The concrete will form part of the roof of Chaplin Station.  To ensure the continuity and integrity of the activity, and to minimize the impact to TTC operations, the pour will be conducted overnight when traffic is lighter.  Some traffic restrictions will be in effect to accommodate equipment and truck access requirements.  Read more »

April 102019

Update: Resumption of Construction at Chaplin Station Tertiary Entrance

Update: Resumption of Construction at Chaplin Station Tertiary Entrance

In April 2019, crews will be resuming work at the Tertiary Entrance site, located east of Chaplin Crescent on the south side of Eglinton Avenue adjacent the old Toronto Fire Hall.  Pile installation of the north wall of the Tertiary Entrance (at Eglinton Avenue) will commence.  Pedestrians rerouting and truck staging will be in effect.  Please read ‘What to Expect’ below.

Upcoming Construction Configuration Read more »

April 052019

Resumption of Construction at Chaplin Station Tertiary Entrance April 2019

Resumption of Construction at Chaplin Station Tertiary Entrance

April 2019

 

What Work is Taking Place?

In April 2019, crews will be resuming work at the Tertiary Entrance site, located east of Chaplin Crescent on the south side of Eglinton Avenue adjacent the old Toronto Fire Hall.  The site will be used for trucks, equipment and material storage.  Read more »

March 282019

Construction Notice: Intersection Closure for Overnight Concrete Pour

Intersection Closure for Overnight Concrete Pour

Chaplin Cres & Eglinton Ave
Saturday April 6, 2019
Read more »

March 192019

Central West Open House (Fairbank to Eglinton Stations)

Thank you for attending the Central West Open House on March 18, 2019. For those of you who missed it, the presentation is here:

 

Download the presentation