April 082020

Spring Open House: Central - March 23, 2020

Thank you for your interest in the Central Virtual Open House on March 23, 2020. The presentation is here:

Read more »

April 072020

Temporary Parking Removal and Lane Closure for Equipment Unloading at Chaplin Station Wednesday April 8, 2020

What Work is Taking Place?

On Wednesday, April 8, 2020, a mobile crane will be delivered to the Chaplin Station Main Entrance site.  The crane will travel north on Chaplin Crescent to Spadina Road, turn onto New Haven Drive and continue south on Gilgorm Road.  The crane will be used to unload equipment from Eglinton Avenue into the site.  Once the equipment has been unloaded, the crane will be removed from the site following the same route.  Read more »

April 032020

Update: Notice of Chipping at Chaplin Station Extended through April 8, 2020

What Work is Taking Place?

Chipping of a concrete pile wall between the Chaplin Station Tertiary Entrance site and the station box is currently underway.  This work is expected to be complete Wednesday April 8, 2020.  Chipping involves use of an excavator and jackhammer to remove concrete and hardened material. Chipping occurs periodically as deep excavation progresses.  Noise and vibration can be expected. Read more »

March 132020

Notice of Chipping at Chaplin Station March 16 – 20, 2020

What Work is Taking Place?

On Monday March 16, 2020, crews will begin demolition of a concrete pile wall between the Tertiary Entrance and station box, located on the south side of Eglinton Avenue adjacent the old fire hall.  Using an excavator and jackhammer, concrete will be removed from grade level to beneath the station roof.  This activity will take approximately five (5) days to complete.  Noise and vibration can be expected.

Hours of Work Read more »

March 052020

Chaplin Avenue CLC Presentation Deck - March 4, 2020

Construction Liaison Committee of Chaplin & Avenue was held on March 4, 2020. You can see the presentation here.