Concrete Pour at Caledonia Station March 11, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
March 11, 2020

 

What Work is Taking Place?

On Wednesday March 11, 2020, crews will at Caledonia will be pouring concrete to form a wall in the future station’s Main Entrance. During the pour, westbound Eglinton Ave W will be reduced to one (1) lane only between Blackthorne Ave and Gabian Way. Lane reductions will begin as early as 10:00am and last until approximately 4:00pm.

Hours of Work

What to Expect

 

Construction Staging

Caledonia Pour March 11 2020

Stay Informed

Sign up for email updates at www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton Corridor.