Concrete Pour at Fairbank Station - August 27, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
August 25, 2020

Concrete Pour at Fairbank Station Aug 27

What Work is Taking Place?

Crews at Fairbank continue to perform large concrete pours. On Thursday August 27, crews will be pouring the last structural wall, from track to concourse level!

Work will begin as early as 6:00 a.m. and the pours will be ongoing for approximately 10 hours. Concrete pumps will be placed within the Main Entrance work zone. Concrete trucks will be staged on Dufferin Street, south of Eglinton Avenue West. Dufferin Street and Eglinton Avenue West will remain open while this work takes place.

What to Expect

Concrete trucks will be staged on Eglinton Avenue West; access to properties along Eglinton Avenue West, Dufferin Street, and Vaughan Road will be maintained. Noise from construction equipment, such as concrete trucks and construction vehicles, can be expected.  

HOURS OF WORK

  • Thursday August 27
  • The concrete pours will begin as early as 6:00 a.m. and last for approximately 10 hours
  • The contractor may not always work during the permitted hours but may do so at its discretion
  • Work may be rescheduled due to weather or unforeseen circumstances
  • This work may be longer or shorter than expected

PEDESTRIAN DETAILS

  • Periodic sidewalk interruptions – pedestrians will be rerouted to temporary sidewalk
  • All TTC bus stops will remain in their current locations

TRAFFIC DETAILS

  • Concrete trucks will be staged on Eglinton Ave W within the Main Entrance work zone and on Dufferin St, south of the Eglinton Ave W.
  • Dufferin St and Eglinton Ave W will remain open

 

Disponible en français.

Sign up for e-mail updates at www.thecrosstown.ca/sign-up