Concrete Pour at Fairbank Station - September 17, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
September 16, 2020

What Work is Taking Place?

Crews at Fairbank continue to perform large concrete pours. On Thursday September 17, crews will be pouring concrete for paving and road restoration works! Work will begin as early as 7:00am and the pour will be ongoing for approximately six hours. Concrete pumps will be placed within the Main Entrance workzone. Concrete trucks will be staged on Eglinton Ave W, east of Dufferin St. Dufferin St and Eglinton Ave W will remain open while this work takes place.

What to Expect

Concrete trucks will be staged on Eglinton Ave W. There will be no additional impacts to traffic or TTC routes. Access to properties along Eglinton Ave W, Dufferin St, and Vaughan Rd will be maintained. Noise from concrete trucks can be expected.

 

TRAFFIC IMPACTS

  • Concrete trucks will be staged on Eglinton Ave W, east of Dufferin St, west of Northcliffe Blvd.
  • Traffic control personnel will be present while this work takes place.
  • Dufferin St and Eglinton Ave W will remain open.
  • No impacts to TTC bus services.

 

PEDESTRIAN IMPACTS

  • Periodic sidewalk interruptions – pedestrians will be rerouted to temporary sidewalk
  • All TTC bus stops will remain in their current locations

 

HOURS OF WORK

  • Thursday September 17
  • The concrete pours will begin as early as 7:00am and last for approximately six hours.
  • The contractor may not always work during the permitted hours but may do so at its discretion.
  • Work may be rescheduled due to weather or unforeseen circumstances.
  • This work may be longer or shorter than expected.

 

OTHER IMPACTS

  • Noise from construction equipment such as concrete trucks and construction vehicles.