Concrete Pour at Mount Pleasant Station Wednesday May 15, 2019

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
May 10, 2019

On Wednesday May 15, 2019, crews will perform a concrete pour in the southeast work zone at Mt Pleasant Road and Eglinton Avenue.  The concrete will form part of the roof of Mount Pleasant Station.  A concrete pump will be set up within the work zone, and concrete trucks will stage on the south side of Eglinton Avenue, east of Taunton Road, while this work takes place.  To ensure the integrity and continuity of the pour, work will begin early at 5:00 a.m.

Details                                  

  • Wednesday May 15, 2019 beginning at 5:00 a.m. for approximately eight (8) hours
  • In the event of inclement weather or delay, this activity will be rescheduled


Construction Staging

 

 

What to Expect

  • One concrete pump will be stationed in the east end of the southeast work zone
  • 8+ concrete trucks are expected per hour
  • Concrete trucks will stage within the work zone and on the south side of Eglinton Ave, east of Taunton Rd
  • Noise from construction activity can be expected

 