What Work is Taking Place?

Crews at Fairbank continue to perform large concrete pours. On Thursday December 17, work will begin as early as 7:00am and the pour will be ongoing for approximately five hours. Concrete pumps will be placed in the laneway parallel to Eglinton Ave W, south of the intersection. Concrete trucks will be staged on Dynevor Rd. The laneway parallel to Eglinton Ave W between Dynevor Rd and Dufferin St will be closed for the duration of the pour. **DELAYED** On Friday December 18, 2020, crews will be pouring a wall within the station box. Work will begin as early as 7:00 a.m. and the pour will be ongoing for approximately ten hours. Concrete pumps will be placed within the Secondary Entrance work zone. Concrete trucks will be staged on Dufferin Street, north of Eglinton Avenue West within the work zone. Dufferin St and Eglinton Ave W will remain open while this work takes place.

 

What to Expect

On Thursday, concrete trucks will be staged on Dynevor Rd. Access to properties along Eglinton Ave W, Dufferin St, and Dynevor Rd will be maintained. **DELAYED**On Friday, concrete trucks will be staged on Dufferin Street. Access to properties along Eglinton Avenue West and Dufferin Street will be maintained. Noise from concrete trucks can be expected.

 

HOURS OF WORK

  • Thursday December 17, as early as 7:00am and for approximately five hours
  • **DELAYED**Friday December 18, as early as 7:00am for approximately 10 hours
  • The contractor may not always work during the permitted hours but may do so at its discretion
  • Work may be rescheduled due to weather or unforeseen circumstances
  • This work may be longer or shorter than expected

 

TRAFFIC DETAILS

  • On Thursday December 17

The laneway between Dufferin St and Dynevor Rd will be closed to all vehicular traffic for the duration of the pour
Concrete trucks will be staged on Dynevor Rd

  • **DELAYED**On Friday December 18

Concrete trucks will be staged on Dufferin St, north of Eglinton Ave W within the work zone.
Dufferin St and Eglinton Ave W will remain open

 

PEDESTRIAN DETAILS

  • Periodic sidewalk interruptions – pedestrians will be rerouted to temporary sidewalk