Construction Notice - Mount Pleasant Station - Traffic Change Hybrid - May 2018

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
May 11, 2018

Traffic Change at Mount Pleasant Station

What Work is Taking Place?

As early as May 23rd, 2018, crews will implement a new traffic stage at Mt. Pleasant Road and Eglinton Avenue East.  Traffic on Eglinton Ave will be shifted to the center and traffic on Mt. Pleasant Rd will be shifted to the east.  This change will make way for completion of storm sewer installation as well as piling preparation, which includes guide wall installation and equipment staging. The north-south crosswalk on the west side of Mount Pleasant and Eglinton Ave E will be closed for the duration of this stage. The north-south crosswalk on the east side will open. The east-west crosswalks along Eglinton Ave E will remain open.

This traffic stage is expected to last for approximately one (1) month.

Upcoming Construction Staging

Hours of Work

  • Permitted construction hours are 7:00 a.m. to 11:00 p.m., Monday to Sunday

What to Expect

  • Noise from construction activity
  • Heavy construction equipment and material storage within work zones
  • Fencing, concrete barriers, dust cloth and scaffolding

Traffic Details

  • Traffic on Eglinton Ave E will be shifted to the center and traffic on Mt. Pleasant Rd will be shifted to the east.
  • Pedestrian rerouting around work zones will be in effect.
  • Taunton Road will remain closed at Eglinton Ave E.

 

For more information, please contact Natalie Ardanaz at the East Community Office.

Disponible en francais