November 26, 2019

*Dates changed - Updated on November 28*

What Work is Taking Place?

As early as Saturday, November 30, 2019, a new traffic configuration will be implemented at Allen Road and Eglinton Avenue West to accommodate construction of Cedarvale Station. Eglinton Avenue West will be reduced to one westbound lane between Park Hill Road and Allen Road South. The dedicated eastbound left turn lane for the TTC bus loop and Allen Road North will remain during this traffic stage.

The traffic change will begin as early as 8 p.m. and take approximately twelve (12) hours to complete.This configuration will be in place for approximately four (4) months until March 2020. During this stage, a mobile crane will be erected within the main entrance site located on the north side of Eglinton Avenue between Park Hill Road and Allen Road South. A new work zone will be erected on Eglinton Avenue, immediately south of the existing main entrance site and sidewalk, to provide a clearance area for the crane which will facilitate the safe loading of construction materials and equipment into main entrance.

All pedestrian routes will remain the same. Concrete barriers and fences will be put in place to delineate pedestrians from work zones. To ensure pedestrian safety, traffic control personnel will be present while the crane is lifting live loads. During these activities, pedestrians may experience intermittent sidewalk interruptions.

Details

  • As early as Saturday, November 30, 2019 for approximately three (3) months.
  • The traffic change will begin as early as 8 p.m. and take approximately twelve (12) hours to complete.
  • This configuration may be in place shorter or longer than expected.

Upcoming Traffic Configuration

 

 What to Expect

  • A new work zone will be erected on Eglinton Ave W between Park Hill Rd and Allen Rd S
  • Noise, lighting, and traffic delays can be expected while the changes are being implemented.
  • Traffic control personnel and/or a paid-duty officer will be present while the new configuration is implemented.

Traffic Changes

  • Traffic on Eglinton Avenue West will be reduced to one westbound lane and two eastbound lanes between Park Hill Rd and Allen Rd S.
  • The eastbound left turn lane will remain for TTC buses turning into Eglinton West Station.
  • The eastbound left turn lane will remain for vehicles turning onto Allen Road North.

Pedestrian Impacts

  • All pedestrian routes will remain the same.
  • While lifting live loads, traffic control personnel will be present to ensure pedestrian safety.
  • Intermittent sidewalk interruptions while lifting live loads.

Transit Information

  • Access to Eglinton West Station will be maintained at all times.
  • Visit www.ttc.ca for more information.

Travelling Smart during Construction

Travel delays are expected with the Crosstown construction. Please allow extra time for your journey. Traffic will be extra heavy at peak periods during the Crosstown construction. When possible, please travel during the off-peak period between 10 a.m. and 3 p.m.


Disponible en français

For more information, please contact the West Community Office.

Thank you for your patience as we work to build this important project.

Please support your local businesses during construction.

Sign up at www.thecrosstown.ca/sign-up to receive regular email updates and download the aCrosstown traffic app to get real-time traffic information for the Eglinton corridor.