Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
February 012019

New Traffic Configuration: Wilson Brook Culvert East of Sloane Avenue

WHAT WORK IS TAKING PLACE?

Work on the Wilson Brook Culvert has been underway since late August 2018 on Eglinton Avenue East. Crews are building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. 

As work progresses, two new traffic configurations will be implemented (depicted below). The first stage will be implemented as early as February 8th, 2019 for up to two (2) weeks and the second stage will then be in place for up to four (4) weeks. Read more »

January 312019

Massey Creek Culvert Work Begins

Latest Update: February 7, 2019

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. This work is expected to begin as early as mid-February 2019 for approximately six (6) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Read more »

January 312019

Updated: Hydro Utility Relocation between Birchmount Road to Kennedy Road

What Work is Taking Place?

In support of construction of the future Crosstown Light Rail Transit, crews will continue relocation and upgrading of existing overhead and underground utilities between Birchmount Road and Kennedy Road. Work began in June of 2017 and will continue for another six (6) months. Read more »

January 282019

CROSS PASSAGE 10 CONSTRUCTION WORKS

Starting as soon as February 4th, an assessment of the existing dewatering system will take place at the Cross Passage site between Lillian Street and Redpath Avenue. Assessment works will take approximately five (5) days. Following the assessment the dewatering system will be recommissioned and will operate on a 24 hour basis. Periodic maintenance will be required.

 

TRAFFIC, TTC AND PEDESTRIAN IMPACTS Read more »

January 252019

Overnight Storm Sewer Connection Work at Brownlow Ave January 2019

What Work is Taking Place?

On January 30, crews will return to Brownlow Ave and Eglinton Ave to connect to the new storm sewer system installed last year.  Concrete will be removed so that crews can access the manhole below ground.  From there, concrete chipping and reforming will take place allowing the crews to connect to the new storm sewer infrastructure.  This work will be performed 24 hours per day.

Hours of Work Read more »

January 242019

MONITORING INSTRUMENT INSTALLATION OAKWOOD STATION

 

WHAT WORK IS TAKING PLACE

Crews are required to replace two monitoring instruments in the Oakwood Avenue and Eglinton Avenue West intersection.

  Read more »

January 242019
January 222019

Reopening of North End of Existing East Platform at Kennedy GO Station

What Work is Taking Place?

Kennedy Station is an interchange station with connections to the GO Transit Stouffville Line, the TTC Scarborough RT, the TTC Bloor-Danforth subway, and a TTC bus terminal. Construction of the Eglinton Crosstown LRT Kennedy Station will include upgrades to the existing Kennedy Station infrastructure. Read more »

January 222019

Traffic Deck Replacement at Eglinton West Subway Station (Cedarvale)

What Work is Taking Place?

  • Crews will be replacing the road decking on the north side of Eglinton Avenue from Park Hill Road to Allen Road South.

Hours of Work Read more »