Construction Updates

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
November 172020

Sidewalk Construction at Eglinton Ave E and Hakimi and Lebovic Ave - East Side

 

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Hakimi and Lebovic Ave intersection. Work on the east side of the intersection is expected to begin November 18, 2020 for a period of one week.

What to Expect

November 172020

Weekend Rail Delivery at Chaplin Station - November 21 & 22, 2020

Weekend Rail Delivery at Chaplin Station

What Work is Taking Place?

On Saturday November 21 and Sunday November 22, material delivery of rigid rail will take place at Chaplin Station. Work will be within regular working hours, with no changes to existing traffic configurations.

What to Expect

November 132020

Paving on Eglinton Avenue East at Don Mills Rd - November 17, 2020

 

 

What Work is Taking Place?

Crews will be performing paving activities on Eglinton Avenue East at Don Mills Road. To accommodate these activities, a short-term traffic change will be implemented. 

 

What to Expect Read more »

November 132020

North and South Platform Shelter Installation at Sunnybrook Stop

 

November 18, 2020  

       

What Work is Taking Place?

November 132020

Science Centre Station Traffic Change at Don Mills Road and Eglinton Avenue East

What Work is Taking Place?

Crews will be performing road reconstruction works at the intersection. To accommodate these activities, a traffic change will be implemented and remain in place for approximately two weeks.

What to Expect

November 132020

UPDATE: Extended Hours at Laird Station

What Work is Taking Place?

Overnight working hours began at the main entrance on September 30, 2020. It has now been extended through to December 18, 2020. Permanent works at the Main Entrance will take place 24 hours a day, Monday through Friday. The current extended hours (6:00 a.m. – 1:00 a.m.) at both entrance shafts and in the tunnels, will continue through to the end of the year. Read more »

November 132020

Crane Footing Removals at Oakwood Station - November to Mid-December 2020

Crane Footing Removals at Oakwood Station

What Work is Taking Place?

Disassembly and removal of the overhead gantry crane is complete at Oakwood Station. Completion of this work allows crews to begin removing the gantry crane footings from the station's Main Entrance site.

November 132020

Concrete Pour at Laird Station - November 14, 2020

 

 

What Work is Taking Place?

Beginning November 14, 2020, crews will perform a concrete pour at the main entrance work zone at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m. 

 

What to Expect Read more »

November 132020

Sidewalk Construction at Eglinton Ave E and Warden Ave - November 16

 

What Work is Taking Place?

Crews will be constructing final sidewalks at the four corners of the Eglinton Ave E and Warden Ave intersection. Work on the west side of the intersection is expected to begin as early as November 16, 2020 for a period of one week. Work on the east side of the intersection is expected to begin as early as November 24, 2020 for a period of one week. 

November 132020

Lane Reductions for Sidewalk Restoration at Keelesdale Station November 9 – 20, 2020

What Work is Taking Place?

Crews at Keelesdale Station have reopened the road and completed the implementation of the final traffic configuration! Over the next few months, crews will continue with finishing activities, including final sidewalk restoration, tree planting, and street cleaning.