October 262020

Berwick Road Closure for Concrete Pour

What Work Is Taking Place?

On Monday October 26, 2020, Berwick Avenue will be closed at Yonge Street while a concrete pour will be carried out at the Berwick Portal site.  The concrete will form part of the portal foundation.  A concrete pump will be placed on Berwick Avenue and several concrete trucks will enter the site each hour.

What to Expect

October 262020

Road Restoration Works at Mt Pleasant Road and Eglinton Avenue East - October 27, 2020

 

 

 What Work is Taking Place?

On Tuesday October 27, crews at Mount Pleasant Station will perform road restoration works along Eglinton Avenue East, east and west of Mount Pleasant Road. As part of this work, crews will be paving potholes and smoothing out bumps at the intersection. Read more »

October 222020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late December 2020

 

 

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late December 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work.

 

What to Expect Read more »

October 212020

Update: TTC Bus Rerouting at Eglinton Station - Extended to Late-Fall 2020

 

 

What Work is Taking Place?

The Eglinton West Station bus loop remains closed while crews perform roof construction for the future Cedarvale LRT Station. Roof construction, currently underway on the east side of the bus loop, has been extended by approximately two (2) months, into late-Fall 2020. During the closure, the 32D Eglinton West bus will continue to extend to Eglinton Station.  Read more »

October 212020

***POSTPONED *** Test Pits at Weston Road and Hollis Street - October 22 & 23, 2020

 

What Work is Taking Place?

Crews at the Rail Corridor continue west Rail Corridor development, including utility installations. On Tuesday, October 27 & Wednesday, October 28, crews will continue to do test pits on Weston Road and Hollis Street. All current traffic restrictions will remain in place.  

 

What to Expect