Guideway Work along Surface Section of the Eglinton Crosstown LRT: Warden Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the centre of Eglinton Avenue East between Warden Avenue and Birchmount Road. Starting as early as mid-March 2019 for approximately eight (8) months.

The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops.

Stage 2 Read more »

March 042019

New Traffic Configuration: Eglinton Avenue East at Jonesville Crescent

WHAT WORK IS TAKING PLACE?

As utility installations progress along Eglinton Avenue East between Bermondsey Road and Victoria Park Avenue, four (4) new traffic stages will be implemented at Jonesville Crescent to accommodate the work zones (depicted below). Traffic will shift to the first stage as early as Monday, March 4th, 2019. Each stage will last approximately one (1) week. Read more »

March 012019

Overnight Lane Closures on Yonge Street for Toronto Hydro Infrastructure Access

What Work is Taking Place?

Crews need to access a cable chamber on the southbound lane of Yonge Street as part of Toronto Hydro utility relocation works. In order to safely carry out the work, the southbound lane on Yonge Street will be closed while crews are accessing the chamber.

 

Hours of Work Read more »

March 012019

Tower Crane Installation at Science Centre Station

Tower Crane Installation at Science Centre Station

WHAT WORK IS TAKING PLACE? Read more »

February 282019

Short Duration Water Shut Off - Avenue Station

Short Duration Water Shut Off

Sunday March 3rd, 10:00 p.m. to 6:00 a.m.

 

WHAT WORK IS TAKING PLACE?

 

Crews at Avenue Station will complete minor works on a local water main from approximately 10:00 p.m. on Sunday March 3rd to 6:00 a.m. on Monday March 4th.  

 

During the works, there will be a temporary water shut off that will last up to ten (8) hours. During this time, there will be no water available from the taps or toilets. Read more »

February 282019

Temporary Traffic Bridge Installation at Mount Pleasant Station

What Work is Taking Place?

As early as Monday March 4, 2019 crews will begin assembling and installing a temporary traffic bridge within the southeast corner of Mt Pleasant Road and Eglinton Avenue East. Read more »

February 282019

Duct Bank Concrete Pour of Guideway from Eglinton Square to Pharmacy Avenue

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »

February 262019

Updated: Upcoming Traffic and Pedestrian Changes At Eglinton West Subway Station (Cedarvale)

Originally Posted: February 13, 2019

Updated: February 26, 2019

As early as March 1, 2019 the area around Eglinton West Subway Station (Cedarvale) will see another round of changes to accommodate replacement of the traffic deck on Eglinton Avenue West at Winnett Avenue and continued shoring activities on Eglinton Avenue at Strathearn Road. 

Hours of Work Read more »

February 252019

Overnight Invert Concrete Pours at Kennedy Station

What Work is Taking Place?

As part of continued support for the future Kennedy Station portal construction, crews will be delivering and pouring cement along Eglinton Avenue East between Ionview Road and Kennedy Road on Thursday, February 28, 2019 from 4:00 a.m. until 4:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west Eglinton Avenue East.

Stage 1 Read more »

February 222019

Eglinton Avenue West Lane Restriction for Signal Installations at Cedarvale Station

What Work is Taking Place?

To accommodate upcoming shoring activities for the new Cedarvale LRT Station, crews will be relocating and installing new traffic poles and signal equipment along Eglinton Avenue West from Everden Road to Allen Road North.